Gaeilge

Minor Flood Mitigation Works and Coastal Protection Scheme

The Minor Flood Mitigation Works and Coastal Protection Scheme (Minor Works Scheme) was introduced by the Office of Public Works in 2009.

Purpose of the Minor Works Scheme

The purpose of the Minor Works Scheme is to provide funding to Local Authorities towards undertaking studies and/or works within their administrative areas for:

  • minor flood mitigation measures to address and manage localised flood risk to properties from fluvial, coastal/tidal and groundwater sources, and
  • coastal protection (erosion) problems – for example, ‘hold the line’ or ‘manage the retreat’.

There are three broad categories of projects funded under the Minor Works Scheme: studies, works, or studies and associated works. The Minor Works Scheme generally applies where a solution can be readily identified and achieved in a short time frame.

The Scheme is also available for local authorities to introduce interim measures for those communities, where a major flood relief scheme is planned, but not yet complete. Applications for interim measures will only be considered up to the time of an application for planning consent for a major scheme.

The Local Authority is responsible for the delivery of the project, including obtaining all required consents and ensuring flood/erosion risks are not caused elsewhere by the proposed works.

Exclusions from the Scheme

Funding under the Minor Works Scheme does not include:

  • studies or works that provide land drainage or flood management to lands alone,
  • costs of the ongoing maintenance of works completed with funding approved under the Minor Works Scheme,
  • reinstatement of approved works through the Minor Works Scheme that have not been maintained,
  • studies and works for flood risk that are not the responsibility of the OPW, including:
    • from surface/storm water/combined drainage systems, that are the responsibility of local authorities/Uisce Éireann,
    • unblocking drains/gullies, that are the responsibility of local authorities/Uisce Éireann,
    • emergency response measures, that are the responsibility of local authorities and the Minister for Housing, Local Government and Heritage, and
    • maintenance of channels and at bridges that are the responsibility of State Agencies, including the maintenance of Drainage Districts (responsibility of local authorities), and road/rail bridges that are the responsibility of Transport Infrastructure Ireland/Irish Rail.

Under the Scheme, applications for funding, from a Local Authority Chief Executive or Director of Services, are considered for projects up to €2 million each, and studies up to €750,000 each.

The OPW’s contribution to approved projects is 90% for the first €300,000 approved and increases to 95% for the balance of approved funding above €300,000 up to €2 million. Any expenditure for projects above the approved limits (and approved amounts for individual applications) remains the responsibility of the Local Authority to provide from their own resources to complete the study/works.

Applications are assessed by the OPW having regard to specific criteria, which includes both technical and economic criteria for the overall project. The economic criteria includes the works achieving a benefit cost ratio of 1 or parity, using the prescribed valuations for the scheme.

The application and approval process is subject to the amount of funding sought and type of works. For studies and works up to €750,000, called Band 1 projects, there are two application forms, one for flood (coastal and non-coastal) related projects and a separate form for coastal erosion related projects. The OPW will assess Band 1 project applications against the scheme’s criteria, having regard to the national programme for flood relief schemes and the work underway on the development of a National Coastal Change Management Strategy.

For those works (study and works) for flood mitigation projects above €750,000 up to €2 million, called Band 2 projects, a three step governance framework is applied:

  • the first step is for local authorities to submit a business case for the proposed works/studies.
  • approval to proceed will include advancing the project to submission for planning, where approval to submit to planning is required.
  • subject to planning consent, approval to proceed to construction is the third approval gateway.

At each gateway, the OPW will assess Band 2 project applications against the scheme’s criteria and the national programme for flood relief schemes and the work underway on the development of a National Coastal Change Management Strategy. The criteria for the Minor Works Scheme will be kept under review by the OPW.

The table below shows a list of projects for which funding has been approved. Further information and the application forms to the Minor Works Scheme are available on gov.ie

Last Updated: 02/06/2026

Local Authority Project Location Project Details Approved Funding (€) Approval Year
Cork County Council Roches Point Sea Wall Detailed Design & Construction of a Toe Wall to stabilize existing sea wall 9,654 2023
Cork County Council Cape Clear Island South Harbour Cork County Council propose to carry out remedial works required to existing Sea Wall at Cape Clear, Co Cork 162,900 2024
Cork County Council Cape Clear Island South Harbour Cork County Council propose to carry out remedial works required to existing Sea Wall at Cape Clear Co. Cork. 26,100 2025
Cork County Council Finure-Guileen Cliff Progress project to detailed design and construction stage for cliff stabilisation works to include fill with rock armour protection at the toe and associated works. 495,000 2024
Cork County Council Kilumney Village Study 27,000 2018
Cork County Council River Ilen Skibbereen Replace the 36m of culvert in private lands 72,000 2015
Cork County Council Roches Point Sea Wall Detailed Design & Construction of a Toe Wall to stabilize existing sea wall 68,445 2022
Cork County Council Ballymakeera Sand bag flood defence structure 187,248 2018
Cork County Council Coachford Village Culverts are old, under capacity and sections are in bad repair. Study required to investigate the flooding mechanisms, improve capacity and what remedial works are needed to the existing culverts 36,000 2023
Cork County Council Inchigeelagh, Co. Cork Cork County Council propose to selectively clear bankside trees and scrub from Inchigeelagh Bridge to Footbridge c. 1700m each bank. 91,602 2025
Cork County Council Bantry Interim Works Works- mobile pumps, sump chambers, sealing gullies, non-return valves, large sandbags & associated works 101,578 2021
Cork County Council Midleton Northern Relief Road Study 19,000 2013
Cork County Council Mogeely, Co Cork Funding for a study to explore the possibility for the implementation of flood mitigation solutions in the catchment upstream of Mogeely. 116,235 2025
Cork County Council Rathcormac, Co. Cork The works are channel clearance works (374m in total) on the Kilbrien stream and attenuation area and the Shanowen watercourses, which are significantly overgrown and restricting flows. There are also some minor works to the wing walls to improve access to the attenuation area on the Kilbrien stream. 49,899 2025
Cork County Council St. Colum’s Community Hall Ballylickey Construct flood defence wall around the community hall, including slot in flood barriers at access points 18,000 2017
Cork County Council Kilmacahill Cloyne Replacement of culverts and works to watercourses 8,100 2012
Cork County Council N71 Cork Road Skibbereen Replace the existing culvert & upgrade of existing piped system 237,009 2018
Cork County Council Liscarroll Extensive river cleaning & cutting back of all overgrowth along the river banks 28,350 2020
Cork County Council Baurnahulla_Drimoleague, P47 K772 To mitigate flood risk by severing the hydraulic connection between the septic tank and the river if it exists. A CCTV survey to ascertain the tanks integrity. If required, the tank and pipework will be replaced. A non-return value and a permanent sump will be constructed. Ramped entrance to the driveway, banked back to earthen embankments 22,615 2022
Cork County Council Castlemartyr Cork County Council intend to lower the embankment at agreed locations to allow flood water storage for larger events (R. Forrest Land). CCC propose to clean the Kiltha river channel – Any overhanging or fallen trees in the river channel that are an obstruction to flow should be removed. CCC are proposing to conduct river dredging (20m u/s of Factory Bridge to 20m d/s of N25 Bridge). 81,844 2024
Cork County Council Gortroe Youghal Install new drain & deepen and clean existing one Deepening of existing stream channel for 900m 13,500 2009
Cork County Council Ballybrack Stream Douglas Installation of trash screen and reinforced concrete substructure and ancillary works /Replacement of under sized culvert under Church Street 304,200 2010
Cork County Council Ballingeary Tree & shrub removal from Inchinossig Bridge to the Bunsheelin River, on Bunsheelin River from GAA pitch to confluence with the River Lee & in an area known as “The Ford” 22,500 2016
Cork County Council Carrigtohill Carrigtohill Flood Risk Assessment Study 72,000 2011
Cork County Council Gortroe Youghal Install new drain & deepen and clean existing one Deepening of existing stream channel for 900m 45,000 2010
Cork County Council Whitegate Village, Co. Cork Cork County Council propose to procure an Engineering Consultant to conduct surveys and a study, and to make recommendations to mitigate the risk of flooding to properties in Whitegate Village. 107,708 2026
Cork County Council Garranachole Castletownroche Installation of gully trap and perforated drainage pipes & associated works 22,500 2021
Cork County Council Coachford, Co. Cork Additional survey work required that will include a topographical survey of the river/stream courses and CCTV survey of the existing culverts. 30,420 2024
Cork County Council Lower Adamstown Ballinhassig Replace culvert under R613 with a Section 50 compliant culvert. 40,000 2021
Cork County Council Ballingeary & Inchigeelagh River cleaning & maintenance works 40,000 2011
Cork County Council Pilmore Cottages, Youghal Coastal Erosion Risk Management Study prior to funding application for structural measures to prevent or mitigate erosion 135,000 2023
Cork County Council Kilmore, Ballinspittle, Kinsale Replacement of culvert with Section 50 compliant culvert. Review impact of 600mm culvert through the GAA pitches. 150,000 2023
Cork County Council Ballingeary, Co. Cork Selectively clear bankside trees and scrub from The Ford area c. 500m each bank. Selectively clear bankside trees and scrub From Inchinossig Bridge to Bunsheelin River c. 680m each bank. Selectively clear bankside trees and scrub On Bunsheelin River from GAA Pitch to confluence with River Lee c. 310m each bank. 82,021 2025
Cork County Council Inchigeelagh Selectively clear bankside trees & scrub Selectively clear islands where impeding flows to mean low water level 45,000 2012
Cork County Council Ballintubber Lay 940mm of 450mm diameter pipe from the northern boundary of the nursery (Irish Plant Propagation Ltd) to the outfall to existing stream approximately 940m south 225,361 2022
Cork County Council Bantry (IPP) - Phase 2 Proposal is to provide flood barriers to each of 28 properties (41 doors) to prevent water entering the properties during flood events. 70,907 2025
Cork County Council Youghal Front Beach Phase 1A – Refurbish Sea Wall 18,000 2010
Cork County Council Glashaboy River River cleaning works only to improve hydraulic capacity 36,000 2012
Cork County Council Bantry (IPP), the Quays, Wolfe Tone Square South & New Street Proposal to provide Flood barriers at each of the 32 no. doors to prevent water entering properties during flood events. 71,582 2024
Cork County Council Ballintubber Lay 940mm of 450mm diameter pipe from the northern boundary of the nursery (Irish Plant Propagation Ltd) to the outfall to existing stream approximately 940m south 346,500 2018
Cork County Council River Ilen Skibbereen River cleaning 10,000 2011
Cork County Council Skibbereen Flood Risk Assessment & Management Study – Ilen Catchment 120,000 2010
Cork County Council Ballymakeera, Ballyvourney Flood defence structure, with suitable impermeable barrier. Remedial works to 90m of an existing stone wall which will then form part of the flood defences thus removing the need for sandbags at this location. 151,847 2024
Cork County Council Durrus Pre-School ,The Pavillion (IPP) Proposal is to provide Flood barriers at each of 8 no. doors to prevent water entering the pre-school during flood events. 15,366 2023
Cork County Council Pilmore Sluice Youghal Repair / replacement of sluice gate & associated works 34,392 2021
Cork County Council Ballinacurra Works-River Flood Protection from Coolea Road to downstream of Kilnamartyra Road Bridge Installation of debris screen 18,000 2009
Cork County Council Riverstick Replacement of Ballady Culvert 81,000 2012
Cork County Council The Glen Glenbrook Passage West Study & remedial works 99,000 2010
Cork County Council Ballinveltig Curragheen Bridge Replace the existing double culvert with one large culvert of equal width & height Construct an overflow culvert downstream & a land drain 180,000 2017
Cork County Council Crookstown Storm water pumping station, new drainage pipes & associated works 295,027 2021
Cork County Council Bantry Interim Works Additional funding for works- mobile pumps, sump chambers, sealing gullies, non-return valves, large sandbags & associated works 82,339 2022
Cork County Council Inchigeelagh Selectively clear bank side trees & shrubs Clear river bed material 22,500 2016
Cork County Council Bandon River Bandon Town Tree Cutting 27,000 2011
Cork County Council Rossa Rd Skibbereen Upgrade of the Rossa Road culvert trash screen & inlet chamber 37,350 2020
Cork County Council Ballymakeera, Ballyvourney Flood defence structure, with suitable impermeable barrier. Remedial works to 90m of an existing stone wall which will then form part of the flood defences thus removing the need for sandbags at this location. 171,858 2023
Cork County Council Skibbereen Flood Risk Assessment & Management Study – Ilen Catchment River Ilen Catchment Flood Risk Assessment & Management Study: Feasbility Study & Preparation of Draft Flood Risk Plan Flood Plain & Channel Survey 119,000 2011
Cork County Council Bantry Interim Flood Mitigation Measures_Rev2 Proposed Works include: • Mobile Pumps (3No.) • Sump Chambers to assist mobile pump operations • Sealing Gullies at critical locations • Non-return valves to critical storm outfalls • Large Sandbags to mitigate tidal water ingress • Whole time tidal defence Blocks • Underground emergency pump line to Quay wall. 9,140 2025
Cork County Council Bayview B&B, Glandore Stabilize the cliff face with ground anchors and to protect against erosion with a sprayed concrete covering. 225,353 2022
Cork County Council Killeagh Cork County Council propose river cleaning (1,100m approx.) to include tree cutting and removal of overhanging trees and branches, vegetation removal downstream of N25 bridge, and compound channel downstream of N25 to Greenway Bridge. 73,125 2024
Cork County Council Ballintubber To complete the laying 940mm of 450mm diameter pipe from the northern boundary of the nursery (Irish Plant Propagation Ltd) to the outfall to existing stream approximately 940m south. 126,499 2022
Cork County Council N71 Cork Road Skibbereen The replacement of a culvert & upgrade piping systems. 41,211 2022
Cork County Council Ballinacurra Installation of debris screen 5,880 2010
Cork County Council Crookstown Permanent flood walls & embankments 318,600 2010
Cork County Council Ballymakeery / Ballyvourney Removal of overhanging growth & other obstacles to river for 3.4 miles from Ballyvourney Bridge downstream 10,000 2012
Cork County Council Riverstick & Environs Channel Capacity Improvements & Localised Permanent Flood Defences: Clear trees/scrub/gravel along river for 5 miles/ Clean and deepen river/ Construct embankments to protect water treatment plant 90,000 2010
Cork County Council Clonakility Channel capacity improvements 350,000 2010