Gaeilge
The Minor Flood Mitigation Works and Coastal Protection Scheme (Minor Works Scheme) was introduced by the Office of Public Works in 2009.
The purpose of the Minor Works Scheme is to provide funding to Local Authorities towards undertaking studies and/or works within their administrative areas for:
There are three broad categories of projects funded under the Minor Works Scheme: studies, works, or studies and associated works. The Minor Works Scheme generally applies where a solution can be readily identified and achieved in a short time frame.
The Scheme is also available for local authorities to introduce interim measures for those communities, where a major flood relief scheme is planned, but not yet complete. Applications for interim measures will only be considered up to the time of an application for planning consent for a major scheme.
The Local Authority is responsible for the delivery of the project, including obtaining all required consents and ensuring flood/erosion risks are not caused elsewhere by the proposed works.
Funding under the Minor Works Scheme does not include:
Under the Scheme, applications for funding, from a Local Authority Chief Executive or Director of Services, are considered for projects up to €2 million each, and studies up to €750,000 each.
The OPW’s contribution to approved projects is 90% for the first €300,000 approved and increases to 95% for the balance of approved funding above €300,000 up to €2 million. Any expenditure for projects above the approved limits (and approved amounts for individual applications) remains the responsibility of the Local Authority to provide from their own resources to complete the study/works.
Applications are assessed by the OPW having regard to specific criteria, which includes both technical and economic criteria for the overall project. The economic criteria includes the works achieving a benefit cost ratio of 1 or parity, using the prescribed valuations for the scheme.
The application and approval process is subject to the amount of funding sought and type of works. For studies and works up to €750,000, called Band 1 projects, there are two application forms, one for flood (coastal and non-coastal) related projects and a separate form for coastal erosion related projects. The OPW will assess Band 1 project applications against the scheme’s criteria, having regard to the national programme for flood relief schemes and the work underway on the development of a National Coastal Change Management Strategy.
For those works (study and works) for flood mitigation projects above €750,000 up to €2 million, called Band 2 projects, a three step governance framework is applied:
At each gateway, the OPW will assess Band 2 project applications against the scheme’s criteria and the national programme for flood relief schemes and the work underway on the development of a National Coastal Change Management Strategy. The criteria for the Minor Works Scheme will be kept under review by the OPW.
The table below shows a list of projects for which funding has been approved. Further information and the application forms to the Minor Works Scheme are available on gov.ie
Last Updated: 02/10/2026
| Local Authority | Project Location | Project Details | Approved Funding (€) | Approval Year |
|---|---|---|---|---|
| Laois County Council | Manor Road, Mountmellick | Laois County Council propose conducting remedial works on a retaining wall located on Manor Road. | 78,737 | 2026 |
| Laois County Council | Brittas Stream, Clonaslee, Co. Laois | Pre-construction; AA screening of stream/culvert. Culvert design/hydro model (area included in Clonaslee FRS) Construction; Replace existing culvert Brittas stream. Vegetation removal & grading of existing stream from culvert to Clodiagh. | 27,000 | 2026 |
| Laois County Council | River Gully (riverbanks and channel) | The proposed works are located along the river Gully (riverbanks and channel) in Laois covering 6.5km of the river before its confluence with the River Nore. The clearance works starts in Dunmore woods (Grid Ref 638289,683519), continues through the Moyne Estate and finishes in farmland to the West Grid ref 641342,678874) | 45,000 | 2026 |
| Laois County Council | Castletown Bridge | AA Screening to remove silt deposit Silt removal works NIS for further enhancement works | 15,000 | 2026 |
| Laois County Council | Clonaslee Bridge R422 | Removal of gravels from under the bridge deck | 20,700 | 2023 |
| Laois County Council | Shannon Rd Mountrath | To install a new culvert at a higher invert level to the existing culvert | 46,565 | 2020 |
| Laois County Council | River Nore Phase 5 | Removal of deadwood/debris and pruning of trees that are causing restrictions on approximately 1.3km of the River Nore in South Laois from Newbridge to the confluence of the River Erkina. | 25,200 | 2025 |
| Laois County Council | River Nore- New Bridge to Knapbridge | Cleaning of archways at New Bridge on the L1659 at Cloncough, removal of debris & tree pruning | 27,000 | 2018 |
| Laois County Council | Clonnygowan | Construct embankment around properties to prevent flood waters entering properties. Remove exiting low level foot bridge to be replace with precast concrete unit. | 88,200 | 2023 |
| Laois County Council | River Nore - New Bridge to Knapton Bridge | Cleaning of archways at New Bridge on the L1659 at Cloncough, removal of debris & tree pruning | 55,373 | 2017 |
| Laois County Council | Moneymore | Construct embankment around properties to prevent flood waters entering properties. BCR 1.50 Financial benefit 90500.00 | 54,000 | 2023 |
| Laois County Council | Teinweir, Co. Laois | Removal of deadwood/debris and pruning of trees that are causing restrictions on approximately 3.5km of the River Nore in South Laois from the townland of Teinweir off the N77 642422.65E, 675835.151N (where phase 3 works ended) to Laois County bounds with Kilkenny 643986.268E,673629.116N. This section of River Bounds County Laois on the East Bank and County Kilkenny on the West Bank. | 55,800 | 2024 |
| Laois County Council | Whitehorse River, Mountrath | Removal of deadwood/debris and pruning of trees that are causing restrictions on approximately 6.5km of the White horse River Co. Laois from Mountrath Town | 58,500 | 2023 |
| Laois County Council | River Nore - Phase 2 | Removal of deadwood/debris and pruning of trees that are causing restrictions on approximately 6km of the River Nore in South Laois | 63,000 | 2022 |
| Laois County Council | Water Castle bridge to Tinwear | Removal of deadwood/debris and pruning of trees that are Causing restrictions on approximately 6.5km of the River Nore in South Laois from Watercastle Bridge in the townland of Abbeyleix Demesne | 63,000 | 2023 |
| Laois County Council | Stradbally | Repoint walls, culvert works, fit a non-return value | 14,400 | 2010 |