The Minor Flood Mitigation Works and Coastal Protection Scheme was introduced by the Office of Public Works in 2009. The purpose of the scheme is to provide funding to Local Authorities to undertake minor flood mitigation works or studies to address localised flooding and coastal protection problems within their administrative areas. The scheme generally applies where a solution can be readily identified and achieved in a short time frame.
Under the scheme, applications are considered for projects that are estimated to cost not more than €750,000 in each instance. Funding of up to 90% of the cost is available for approved projects. Applications are assessed by the OPW having regard to the specific economic, technical social and environmental criteria of the scheme, including a cost benefit ratio.
Works that are normally the responsibility of the local authorities will generally not be considered for OPW funding. Where such works would also mitigate the risk of flooding to properties, partial funding may be considered by OPW. The Local Authorities must be satisfied that the works will not have a significant impact on flood risk elsewhere. The commencement and progression of any works for which funding is approved is a matter for each Local Authority concerned.
The table below shows a list of minor works projects for which funding has been approved. Minor Works Scheme Explanatory Leaflets and Application Forms can be found on gov.ie
Last Updated: 01/04/2025
Local Authority | Project Location | Project Details | Approved Funding (€) | Approval Year |
---|---|---|---|---|
Galway County Council | Carheens Cross Belclare | Install 600mm pipe | 9,000 | 2010 |
Sligo County Council | Strandhill, Co. Sligo | Proposed further study will provide clarification and additional information on the current problem. | 28,800 | 2025 |
Tipperary County Council | Baynanagh Toomevara | Remove wall, lay piping, construct inspection chambers and roadside gullies. Provide fencing. | 42,210 | 2010 |
Mayo County Council | Cloonmore & Carrowntober, Carracastle, Co. Mayo | Construction of new earth embankment, approximately 0.8 metres in height extending over a length of 75 metres. Cleaning of 186 linear metres of an existing open drainage ditch (along the west side of the L-1306-0) and the construction of a new road crossing/culvert on the L-13063-0, to allow for discharge of the excess flood waters. Accommodation works will be required, involving reconstruction of an existing cattle pin and improvement of an existing culvert at a field entrance. | 14,667 | 2025 |
Galway County Council | Ballinasloe Town Study | Study | 9,000 | 2010 |
Tipperary County Council | Lagganstown | Road drainage system & outfall pipe through hill to natural lake | 18,000 | 2015 |
Leitrim County Council | Tawnylea | General channel maintenance and provision of fencing | 27,000 | 2010 |
Longford County Council | O'Leary Residence Ballinalee | Provide overflow channel to existing drainage | 6,975 | 2011 |
Limerick City & County Council | John Paul Tce Broadford | Construct storm sewer, provide and connect gullies | 15,750 | 2010 |
Limerick City & County Council | Number of locations in Co. Limerick | Purchase and mobilisation of pumps for the Northwest (Shannon Estuary); Northeast (Lower Shannon/Mulkear) and Southeast (Kilmallock-Galtees) regions of the county | 135,000 | 2010 |
Mayo County Council | Glenisland River | Removal of debris/vegetation and associated works | 21,375 | 2011 |
Kerry County Council | Dingle Bay East-Castlemaine Harbour | The procurement of additional survey work | 18,000 | 2020 |
Clare County Council | Ballycorick Ballynacally | Replace existing sluice & headwall, repair embankment | 52,200 | 2019 |
Tipperary County Council | Graigue Clogheen | To intercept storm water, works to include the laying of a 450mm diameter corripipe, backfilling & road reinstatement works | 13,950 | 2017 |
Monaghan County Council | Corfad Ballybay | Constructing/raising of road foundation & associated works | 40,500 | 2018 |
Galway County Council | Derreen Abbeyknockmoy | Construction of a new 450mm diameter piped overflow with two headwalls & a road gully to the existing open drain on the opposite side of the public road to the properties at risk | 6,120 | 2014 |
Carlow County Council | Leighlinbridge | Flood alleviation works along banks of River Barrow at Carlow Road (Lord Bagenal Hotel) & Barrow Track (Garrison House), together with ancillary drainage works | 36,661 | 2012 |
Monaghan County Council | Corleck/Annahaia | Study | 15,000 | 2016 |
Longford County Council | Lisduff, Lanesboro | Divert water from open stream & connect drainage system into existing open drain | 18,000 | 2018 |
Kildare County Council | Mooney's Stream Newbridge | Replace existing culverts with upgrade sections and re-grade existing drains & ditches | 161,483 | 2011 |
Donegal County Council | Meenaniller, L-1363-2 | Upgrading of 600mm pipe with 900mm pipe; Installation of 1200mm pipe; Culvert replacement. | 73,044 | 2010 |
Galway County Council | Rathgorgin Athenry | Installation of pipeline / Provide outfall to local drain / Cleaning of existing drainage channel | 13,500 | 2011 |
Galway County Council | Cloonacauneen | New drainage system | 13,500 | 2010 |
Galway County Council | Ballaun Loughrea | River deepening, cleaning & maintenance. Upgrade River crossing | 67,500 | 2010 |
Galway County Council | Castleblakeney | Upgrade culvert | 9,000 | 2010 |
Roscommon County Council | Lisduff | Excavate 2.1 km of existing channel, including farm crossings | 9,450 | 2011 |
Donegal County Council | Pairc an Grainan Burnfoot | To construct 25m shuttered wall at sewerage treatment plant To reshape corner of embankment to provide better flow | 4,050 | 2013 |
Galway County Council | Kilcloghans Tuam | To construct a reinforced concrete flood defence wall, a 600mm pipe and flap valve to be fitted to the outfall of the existing open land drain to the Clare River | 3,650 | 2017 |
Kilkenny County Council | Seskin Bridge Lisdowney | Replace Culvert | 14,850 | 2012 |
Tipperary County Council | Ardfinnan Clonmel | Works – Strengthening riverbank, raising embankment & removal of vegetation. | 15,636 | 2010 |
Galway County Council | Off R446 at Srah townload, Loughrea | Installation of pipe | 19,800 | 2010 |
Galway County Council | Lakyle Craughwell | Study | 9,000 | 2016 |
Mayo County Council | Carrowholly | Upgrading 3 embankments and road raising | 126,000 | 2022 |
Galway County Council | Drim Village | Provision of adequate drainage | 27,000 | 2010 |
Mayo County Council | Foxford | Works | 31,500 | 2009 |
Tipperary County Council | Carrigeen Cahir | Improvements to Marshes Stream | 26,325 | 2010 |
Galway County Council | Roo, Tierneevin, Gort, Co. Galway | Installation of 60m of embankment with impermeable membrane. Relocation of field access gate away from new embankment location. 20m of low-level concrete block wall. | 12,600 | 2024 |
Leitrim County Council | LP4253-1 Carrowcrin | Channel cleaning | 10,900 | 2012 |
Mayo County Council | Seasonmaster Straide | 175m long raised embankment at site perimeter Raise road surface above adjacent watercourse | 28,575 | 2016 |
Kerry County Council | Ballylongford | Coastal flooding mitigation measures | 92,187 | 2015 |
Donegal County Council | Ballindrait | Construct new twin 900mm sluice Regrade, clean and/or widen existing channel Construct 900mm diameter bypass culvert | 45,900 | 2014 |
Donegal County Council | Magherawarden Burn Portsalon | To direct stream away from the dunes | 20,000 | 2013 |
Wexford County Council | Clone Road Clone Upper | Coastal protection works | 90,000 | 2009 |
Laois County Council | River Nore - New Bridge to Knapton Bridge | Cleaning of archways at New Bridge on the L1659 at Cloncough, removal of debris & tree pruning | 55,373 | 2017 |
Longford County Council | Camlin River Studies | Preparation of Integrated Summary Report of Camlin River Studies | 30,056 | 2011 |
Galway County Council | The Rossaveel Sports Grounds | Galway County Council propose to remove vegetation and blockages from the river from the point where the two rivers merge to a point downstream of the sports ground. From there the river is clear and is in a straight line to the sea. The land is soft bog with rock outcrops and some regrading and removal of rock is required to ensure a constant unrestricted fall away from the sport ground. | 19,800 | 2024 |
Limerick City & County Council | St. Mary's Park, King's island | It was agreed with the Minister and the OPW that a wall of large Sandbags be put in place around Kings Island as an emergency measure to prevent a reoccurrence of the flooding. | 281,063 | 2014 |
Tipperary County Council | Holycross, Thurles | Construct a new surface water storm drain 315m long including manholes and chambers and civils works, outfall to existing open drain. | 77,400 | 2022 |
Roscommon County Council | Mountcampbell Jamestown/Drumsna | Remove trees from river & remove all timber debris below high water contour (approx. 10m) from river bank for a length of 700m | 40,500 | 2017 |
Roscommon County Council | Tibarney | Replace culverts, clean out existing stone culvert including removal of stone debris | 16,200 | 2011 |
Waterford City & County Council | Rathanny Kill | Up-size existing bridge/culvert. Re-shape riverbanks. Re-surface road. | 19,800 | 2010 |
Westmeath County Council | Iona Villas Athlone | Flood defence embankments, emergency pumping stations, installation of penlocks | 177,323 | 2010 |
Limerick City & County Council | Limerick City Quays (Shannon Bridge to Sarsfield Bridge) | Repair works to existing quay walls. Enhancement of ground levels between river and buildings fronting onto the quays. Installation of demountable barriers | 153,500 | 2013 |
Monaghan County Council | Ballybay | Retaining of collapsed retaining structure, flood defences at Fair Green, removal of debris upstream and downstream | 427,500 | 2012 |
Tipperary County Council | St. Johnstown Fethard | Replacement of culvert | 4,500 | 2012 |
Tipperary County Council | Holy Cottage Road, Barnane, Templemore | Construction of 520m of a 450mm surface water pipe along with a number of new gullies & associated works. | 1,241 | 2021 |
Galway County Council | Curra Abbey | Install drainage pipes & replace the old stone culvert with new piped system | 18,000 | 2020 |
Longford County Council | Rathmore Aughnacliffe | Channel cleaning/widening & levee construction | 24,300 | 2010 |
Fingal County Council | The Burrow Portrane | Installation of 380 no. concrete ‘SeaBee’ units to reduce the wave energy reaching the dune face(Temporary interim emergency measures) | 456,464 | 2018 |
Roscommon County Council | Cloghnashade Four Roads | Refurbishment of one road bridge 900mm diameter and one access road bridge 600mm, piping 115m of open drain and maintenance of open drain | 25,000 | 2011 |
Galway County Council | East Bridge Ballinasloe | East Bridge Flood Eyes - Consultant fees for design, procurement of works and land acquisition | 80,796 | 2011 |
Louth County Council | Whitestown | To repair the revetment & associated works | 7,200 | 2013 |
Limerick City & County Council | Coolaboy Dromcolliher | Construct storm sewer, provide and connect gullies | 22,500 | 2010 |
Roscommon County Council | Ogulla River | To carry out maintenance on channel, replace culverts & repair to existing weir structure | 54,000 | 2016 |
Clare County Council | Cloughauninchy | Coastal erosion & flood risk management study | 84,000 | 2015 |
Galway County Council | Rafarn Loughrea | Installation of a surface water drain | 45,000 | 2018 |
Galway County Council | Emmanuel House Clonfert | To construct a flood defence wall & associated works | 20,000 | 2019 |
Clare County Council | Shannon Airport River Defences | To strengthen some 155m of the critical area of embankment using a rock armour revetment in front of the existing embankment | 150,000 | 2011 |
Monaghan County Council | Aghalile-Derryolam | Study | 19,800 | 2018 |
Galway County Council | Cregganore Castledaly | The upgrade & repair of existing culverts & associated works | 29,700 | 2020 |
Mayo County Council | Crossmolina Car Park | To remove existing railing, construct wall & flood barrier & associated works | 95,220 | 2016 |
Galway County Council | Ballinasloe Town Centre | Purchase Temp Flood Defence- Aquadam to be deployed as required, to be available for Galway County also | 96,849 | 2016 |
Kerry County Council | Ballyheigue | Use of rock armour to stabilise the cliff, it will require a concrete toe anchored into rock | 307,910 | 2022 |
Donegal County Council | Inver | Installation of rock armour to protect the existing falling sea wall | 36,000 | 2016 |
Wexford County Council | Ballyhack | Coastal flood defence works, comprising raised sea walls, demountable barriers at opening in sea walls & foul pumping station. (excludes works to provide new combined sewer) | 301,500 | 2016 |
Limerick City & County Council | Gotoon, Kilmallock, | Construct a 375m storm water drain- 450mm diameter | 15,705 | 2021 |
Galway City Council | Coolarne Turloughmore | Replacing of existing 450mm pipe with 400m of 900mm piping 700m open drain required,inlet and outlet required estimated at €125,000. | 112,500 | 2010 |
Clare County Council | Tromara Quilty | Design and build Gabion wall/mattress protection to beach dunes 100m long | 72,000 | 2011 |
Kildare County Council | Confey Leixlip | Upgrade culvert | 66,556 | 2010 |
Meath County Council | Ashbourne (Rathlodge; Racehill Lane; Huntsgrove; Brookville Road; Hunter's Lane; Cedar Road & Milltown Road) | Upgrade culverts at Racehill Lane, Huntsgrove, Brookville Rd & Hunter's Lane. Utilise the existing diversion pipe but limit the flow to 1.2 m3/s. Remove or reconstruct bridge crossing on private land downstream of Racehill Lane. Increase size of open channel adjacent to 29 Huntsgrove Reinstatement of nos 28 and 29 Huntsgrove Increase size of open channel running from Brookville Rd to Hunter's lane. Construct a shallow embankment adjacent to the Broadmeadow River on Milltown Rd (Miller's Cottage) | 450,000 | 2016 |
Cavan County Council | Knockateery Cloverhills | To install new 300 diameter culvert, construct 100m roadside banking edge support, re-construct, raise & resurface 100m of local primary road | 14,850 | 2020 |
Leitrim County Council | Lough Reane / Tully Lough, Fenagh | To provide an overflow connection between Lough Reane & St. John's Lough in the form of combined piped and open channel section | 140,000 | 2013 |
Galway County Council | Clonfert, Ballinasloe | Pipe existing open drains for approximate distance of 124m with 1200mm diameter, clean existing open drains for approximate distance of 315m & associated works | 90,000 | 2022 |
Roscommon County Council | Moore | Install 160m of 600mm diameter pipe with manholes & install culvert | 14,850 | 2016 |
Limerick City & County Council | Feale View (L1326) Abbeyfeale | Construct storm sewer, provide and connect gullies | 28,800 | 2010 |
Clare County Council | Elm Park / Watery Road | Construct higher embankment / Upgrade storm drain | 228,871 | 2012 |
Limerick City & County Council | Broadford Rd Dromcolliher | Construct storm sewer, provide and connect gullies | 15,750 | 2010 |
Kildare County Council | Ardclough | Construction / Replacement of canal & road crossings | 306,410 | 2010 |
Waterford City & County Council | Clodiagh Bridge Portlaw | Raise level of slip to river, form earth bund, construct flood proof gates | 14,850 | 2010 |
Cork County Council | Skibbereen | Flood Risk Assessment & Management Study – Ilen Catchment | 120,000 | 2010 |
Galway County Council | Cloonoo Loughrea | Construct new channel | 2,000 | 2010 |
Sligo County Council | Strandhill | To provide terminal protection works to heavily used main access way to major recreational dune area and southern beach | 290,000 | 2012 |
Monaghan County Council | Drumgossett | To place a new 600 mm diameter storm water pipe line from junction at school | 47,967 | 2009 |
Cork County Council | Ballymakeera, Ballyvourney | Flood defence structure, with suitable impermeable barrier. Remedial works to 90m of an existing stone wall which will then form part of the flood defences thus removing the need for sandbags at this location. | 171,858 | 2023 |
Galway County Council | Baunykav Kylebrack Loughrea | To replace the existing piped section of open drain with circa 150m of 600mm diameter storm water pipeline | 27,000 | 2019 |
Wicklow County Council | The Murrough | To construct a rock armour ramp transition zone between the existing strand and the adjoining shoreline- details as outlined in the RPS Report of February, 2015 | 135,000 | 2015 |
Roscommon County Council | Oran/Killinraghy | Provide and lay pipework, increase the cross-sectional area of existing channel and replace culverts as necessary | 67,500 | 2012 |
Mayo County Council | Carrowholly | Addition of embankments to the existing flood defences, associated works | 358,787 | 2019 |
Galway County Council | Leenaun Village (IPP) | Construction of flood defence walls, IPP for 3 properties not protected by the walls | 198,000 | 2021 |
Limerick City & County Council | Castleconnell / Montpelier | Construction of embankments at Montpelier Installation of mobile/ temporary measures in Castleconnell | 54,000 | 2010 |
Louth County Council | Ardee Road Dundalk | Replacement of storm culvert / River cleaning including cluverts under Railway Bridge and Ardee Road | 54,000 | 2010 |
Cavan County Council | Aghaadreenagh Redhills | Replace damaged culvert 5.5long | 6,750 | 2020 |
Limerick City & County Council | Funcheon Bridge Kilbehenny | Phase 1: Removal of flood retaining debris, and overgrowth on both banks Phase 2 study only | 74,700 | 2020 |
Galway County Council | Caheroyn Drive Athenry | Remove palisade fencing & existing stone wall, construct low stone wall & flood defence wall, construct sump & associated works | 36,000 | 2017 |
Kerry County Council | Ballyheigue | Use of rock armour to stabilise the cliff, it will require a concrete toe anchored into rock. A detailed topographic & bathymetric survey required. | 231,489 | 2020 |
Roscommon County Council | Killeglan Stream | Replace culvert at Onagh & remove growth from Killeglan Stream over distance of 5kms | 64,800 | 2016 |
Galway County Council | Ballyglass Kilconnell Ballinasloe | Clean existing field drains & roadside drains, replace existing pipes with 900mm diameter pipes & associated works | 45,450 | 2017 |
Galway County Council | Middlethird Maree Oranmore | Improve drainage system | 15,840 | 2010 |
Carlow County Council | Tullow | Construction\installation of walls, berms, flood gates along River Slaney / Upgrade drainage system along Thom Traynor Road / Installation of pumps and sumps | 150,000 | 2012 |
Galway City Council | Two Mile Ditch | Construct pump sump & provide mobile pump. Construct pipeline to existing surface water drainage system. | 5,306 | 2012 |
Cork County Council | Gortroe Youghal | Install new drain & deepen and clean existing one Deepening of existing stream channel for 900m | 13,500 | 2009 |
Tipperary County Council | Tivoli Heights Clonmel | Works-Installation of new grill to improve flow, constructionof wing walls to side of culvert/pipe | 18,000 | 2009 |
Roscommon County Council | Athleague | Construct a weir and overflow channel & carry out channel maintenance | 270,000 | 2010 |
Leitrim County Council | Liscoghill Drumkeeran | Clear obstructions up & downstream of the bridge on the local road and the bridge on R200 (Dowra Road) Cut back trees that hang over the river | 21,002 | 2016 |
Cork County Council | Castlemartyr | Cork County Council intend to lower the embankment at agreed locations to allow flood water storage for larger events (R. Forrest Land). CCC propose to clean the Kiltha river channel – Any overhanging or fallen trees in the river channel that are an obstruction to flow should be removed. CCC are proposing to conduct river dredging (20m u/s of Factory Bridge to 20m d/s of N25 Bridge). | 81,844 | 2024 |
Tipperary County Council | Kilroe, Ballylooby | Excavation of approx. 250 metres of a new 1.50m deep drainage ditch | 14,200 | 2012 |
Cork County Council | Youghal Front Beach | Phase 1A – Refurbish Sea Wall | 18,000 | 2010 |
Mayo County Council | Crossmolina Walkway | To remove existing shrubbery, construct walls, supply & install flood gate & associated works | 64,350 | 2016 |
Mayo County Council | Barnagreggaun / Mossbrook, Balla | Clean drains, install pipe & construct banking alongside road | 5,760 | 2015 |
Clare County Council | Mountcatherine | Removal of trees Reconstruction of embankment- set back from channel edge, graded at approximately 1:3 on both sides and flat on top (width of 1.5 to 2m) Associated works | 49,500 | 2016 |
Longford County Council | Mullagh | Clean out existing drain up to 1km, install a 900mm diameter pipe at road crossing next to dwelling to improve flow of water and prevent isolation | 18,000 | 2017 |
Cork County Council | Ballinacurra | Works-River Flood Protection from Coolea Road to downstream of Kilnamartyra Road Bridge Installation of debris screen | 18,000 | 2009 |
Westmeath County Council | The Strand Athlone | Flood defence embankments, emergency pumping stations, installation of penlocks | 288,748 | 2010 |
Galway County Council | Ardmore Kilkieran | Increase capacity instream by widening instream for 150m | 4,500 | 2019 |
Galway City Council | Menlo | Installation of pipe / channel from turlough to River Corrib, together with pumping equipment | 121,995 | 2010 |
Laois County Council | Whitehorse River, Mountrath | Removal of deadwood/debris and pruning of trees that are causing restrictions on approximately 6.5km of the White horse River Co. Laois from Mountrath Town | 58,500 | 2023 |
Roscommon County Council | Red Bridge Drum | Install 600mm pipes under Road l2026 & L7577 | 24,300 | 2010 |
Leitrim County Council | Leitrim Road / Park Lane, Carrick | Upgrading, cleaning and deepening of culverts & drains at Leitrim Road and Park Lane. Provision of deepened culvert west of Park Lane for 150m | 220,860 | 2010 |
Tipperary County Council | Buffanagh Killenaule | Maintenance of river between Buffanagh & Moglass | 13,250 | 2012 |
Tipperary County Council | Marlfield Lake Clonmel | Site Investigation, including culvert systems and design of repair and reconstruction works | 12,600 | 2010 |
Donegal County Council | Fahan Marina | Repair collapsed sea wall | 18,000 | 2010 |
Louth County Council | Bellurgan Dundalk | Placing of rock armour along embankment | 9,000 | 2015 |
Tipperary County Council | Toureen Cahir | Installation of 450mm pipe and 350m of additional land drains | 11,250 | 2010 |
Galway County Council | Ardacong, Tuam | Study | 9,000 | 2016 |
Galway County Council | Ballyhugh Gort | Installation of higher capacity culvert | 22,500 | 2012 |
Kerry County Council | Kilfenora Fenit | Detailed Design Stage | 176,166 | 2018 |
Tipperary County Council | Currabaha | Construct inspection chambers, upgrade existing land drainage pipe. | 9,900 | 2010 |
Galway County Council | Rinville West Oranmore | Drainage maintenance works on approximately 950m of channel | 23,346 | 2015 |
Mayo County Council | Bunnadober Ballinrobe | Deepen & widen the existing open drain for 150m & extend it for 35m south westwards. Extend the roadside embankment along the western side of the channel & associated works | 138,079 | 2017 |
Mayo County Council | Neale-Cross | A prefeasibility study, stage 1feasibility study, preferred option identification & surveys | 51,850 | 2022 |
Clare County Council | Miltown Malbay | To construct a 206m long DN1200 culvert to alleviate flooding Associated Works | 490,500 | 2020 |
Wexford County Council | Seaview, Bastardstown, Co. Wexford | Works to section 3, the last 145m to protect houses to the east of the coastline, consisting of full height Rock Armour. Section 3a. 100m of coastline. | 657,338 | 2024 |
Kilkenny County Council | Mullinavat | Channel clearance, construct walls, remove weir | 72,000 | 2010 |
Galway County Council | Castlegrove Tuam | Minor improvements to Corrib Clare CDS | 21,420 | 2010 |
Kerry County Council | Kenmare (Finnihy & Keelnagower Rivers) | Clearance of vegetation along 0.6km length of the Finnihy & Keelnagower River banks | 41,912 | 2021 |
Waterford City & County Council | Lismore | Use of flood barrier structures, embankment works & improve the hydraulic capacity of the channel at the bridge | 76,217 | 2018 |
Galway County Council | Laurencetown Village Ballinasloe | Channel Improvements | 29,500 | 2012 |
Wexford County Council | Seaview Kilmore | Detailed Design Study | 36,000 | 2021 |
Tipperary County Council | Blackcastle Road Templemore | To install a new 6m culvert beside the existing bridge, river widening & associated works. | 98,100 | 2021 |
Galway County Council | Kiltullagh Claregalway | Install 350m of 300mm double walled pipe from flood location to turlough entry point | 20,250 | 2011 |
Leitrim County Council | R280 Killargue | Channel cleaning | 20,400 | 2012 |
Galway County Council | Sliabhcarran Gort | Installation of 750m of surface water drain | 108,000 | 2018 |
Tipperary County Council | R-690-4 Lismalin | Install new drainage culvert beneath the R69-4 & excavate a new 130m long open drainage ditch on private lands | 10,800 | 2016 |
Galway County Council | Glenaslat Monivea Ballinasloe | Replace existing stone culvert with culvert of larger capacity & regrade existing open drains | 14,400 | 2012 |
Westmeath County Council | Ballynagall | Construction of 900mm pipe from outlet | 45,000 | 2009 |
Cavan County Council | Drummullan | A scheme comprising a combination of earthen embankment, culvert and flood wall defences. | 205,002 | 2018 |
Galway County Council | Kilcolumb (Keeloges West) Glenamaddy | Existing pipe and stone culvert to be replaced with 900mm diameter concrete pipe | 13,500 | 2011 |
Tipperary County Council | Barna Newport | Provide 12” diameter piping at roadside for 250 metres to discharge to soak-pits | 27,180 | 2012 |
Louth County Council | Baltray | Construct/raise embankment wall | 180,000 | 2010 |
Galway County Council | Manusflynn | Construct a 600mm diameter piped road culvert, remove obstructions & associated works | 10,350 | 2015 |
Donegal County Council | Stranorlar-Ballybofey | Vegetation and tree removal on embankment & construction of sumps / pumping areas | 157,500 | 2018 |
Louth County Council | Seabank Castlebellingham | Rock armour protection to 20m of unstable cliff face, rock armour to be approx. 2m high | 24,750 | 2020 |
Galway County Council | Oultort Portumna | Installation of 170m of surface water drain & associated works | 25,650 | 2017 |
Mayo County Council | Owenwee River Westport | Drainage of river, repair weir & provide fencing | 52,200 | 2010 |
Kerry County Council | Tullig Castleisland | Raising of retaining wall, culvert replacement at Tullig, storm water drainage pipe at Kilbannivane & associated works | 58,520 | 2016 |
Galway County Council | Moneenaheeltia Laurencetown Ballinasloe | Upgrade bridge on existing watercourse | 7,245 | 2012 |
Galway County Council | Peake Claregalway | Construct earthen embankment | 4,500 | 2010 |
Galway County Council | Castledaly River | River cleaning & blockages removal | 10,800 | 2020 |
Galway County Council | Ballinamore Bridge | Remove blockages & obstructions | 31,500 | 2011 |
Galway County Council | Dunmore Golf Club | Install 2no flap valves & construct 510m3 retaining pond | 19,800 | 2023 |
Tipperary County Council | Spa Villa Old Spa Road Clonmel | Form temporary dam & concrete bed, provide additional protection to wall, construct clay embankment & associated works | 5,400 | 2014 |
Galway County Council | Derrymullan Ballinasloe | Provide flood defence wall at rear of housing developments & flood defence wall. | 900,000 | 2010 |
Clare County Council | Thomond Villas Clarecastle | Study-detailed design for embankment & road raising | 30,000 | 2020 |
Cork County Council | Liscarroll | Extensive river cleaning & cutting back of all overgrowth along the river banks | 28,350 | 2020 |
Sligo County Council | Lough Nasool | Funding required for a study of the surrounding area as an overflow from the lake is required to prevent further flooding. | 9,000 | 2022 |
Cork County Council | Ballymakeery / Ballyvourney | Removal of overhanging growth & other obstacles to river for 3.4 miles from Ballyvourney Bridge downstream | 10,000 | 2012 |
Westmeath County Council | Aghanargit, Moate | The replacement of a damaged existing piped section of overflow network, including manholes | 16,920 | 2021 |
Kerry County Council | Fenit Road | Fenit Road Coastal Protection Scheme – Rock revetment & buttressing embankments | 360,000 | 2009 |
Laois County Council | Clonaslee Bridge R422 | Removal of gravels from under the bridge deck | 20,700 | 2023 |
Cork County Council | Gortroe Youghal | Install new drain & deepen and clean existing one Deepening of existing stream channel for 900m | 45,000 | 2010 |
Tipperary County Council | Newcastle Clonmel | To replace sections of the existing masonry walls & replace with railing or other approved construction, to reduce risk of flooding of commercial premises using flood walls, gates etc. & fit non-return valves to existing pipe network | 21,600 | 2016 |
Waterford City & County Council | Feddans | Construct a new 450mm diameter culvert under the existing road draining to an existing land drain | 18,000 | 2011 |
Kerry County Council | Emlagh West | To clear channel to increase hydraulic capacity | 6,300 | 2011 |
Galway City Council | Claire River Galway City | Carry out tree cutting & vegetation removal | 33,840 | 2018 |
Longford County Council | Fort William Lanesboro | Install a 600mm diameter pipe over a distance of 640 metres to drain the area | 54,000 | 2016 |
Roscommon County Council | Corroy Knockcroghery | Installation of a 450mm drainage line & associated works | 31,500 | 2018 |
Galway County Council | Caheroyn Drive Athenry | Remove palisade fencing & existing stone wall, construct low stone wall & flood defence wall, construct sump & associated works | 4,500 | 2018 |
Galway County Council | Doonlooughan Pier Ballyconnelly Conemara | Construct coastal protection to the public access road | 153,000 | 2010 |
Donegal County Council | Lower Mount Merrion Milford | Clean open drain | 1,800 | 2016 |
Roscommon County Council | Corraree-Ballygatta | Excavate open drain through land, install 900mm diameter pipes & associated works | 37,800 | 2017 |
Donegal County Council | Portnoo to Dooey Point | Coastal Flooding and Erosion Risk Management Study | 76,500 | 2017 |
Galway County Council | Tonacurra Newbridge Ballinasloe | Replace existing culvert with culvert of larger capacity & regrade existing open drains | 11,250 | 2011 |
Tipperary County Council | Ballylooby | Construct reinforced earth embankment/Masonry wall along river bank within affected property. Install non - return valves on storm pipes draining to river. Install temporary Flood barriers at strategic locations to the affected property. | 25,200 | 2024 |
Wexford County Council | Rosslare Warren Middle | Coastal erosion risk management study | 28,800 | 2015 |
Limerick City & County Council | Glebe (Monagea) | Construct storm sewer, provide and connect gullies | 14,850 | 2010 |
Donegal County Council | Chapel Street Carndonagh | Removal of existing undersized culvert & replace with upsized box culvert, channel improvements & maintenance to the stream | 16,290 | 2014 |
Laois County Council | Moneymore | Construct embankment around properties to prevent flood waters entering properties. BCR 1.50 Financial benefit 90500.00 | 54,000 | 2023 |
Kerry County Council | Flesk River Glenflesk (Phase 1 & 2) | Clearance of vegetation of the river bank between Curreal Bridge at Glenflesk Village to Gortahoosh Bridge & Loo Bridge and associated works | 27,000 | 2019 |
Waterford City & County Council | Clodiagh Bridge Portlaw | Earth bund construction, provision of flood proof gates & raise level of slip adjacent to river | 4,734 | 2018 |
Kerry County Council | Ballyheigue | Use of rock armour to stabilise the cliff, it will require a concrete toe anchored into rock. | 191,730 | 2022 |
Donegal County Council | Rasheeny Culvert Ballyliffen | Replace 3 pipes with a box culvert | 13,500 | 2013 |
Clare County Council | Ballycorick, Ballynacally | Rebuild damaged sections of embankment (130 metres in total) | 46,800 | 2010 |
Louth County Council | Annagassan | To construct rock armour revetment | 10,800 | 2013 |
Galway County Council | Cregganna Oranmore | Install 140m of 300mm diameter pipe and 170m of open drain & associated works | 12,600 | 2018 |
Roscommon County Council | Curnalee | To install pipe The pipe size to be a minimum of 900mm in diameter | 18,000 | 2016 |
Meath County Council | Meath Coastline | A study of the coastal erosion on Meath’s coastline, it is happening at individual properties, directly adjacent to public roads, at our coastal dunes systems and to our beaches. Towns in Mornington, Laytown and Bettystown and also individual properties are at risk of inundation. | 90,000 | 2022 |
Kilkenny County Council | Callan | Construction of flood defence walls & embankments | 270,000 | 2010 |
Roscommon County Council | Moneymore TD Knockcrohery | Drainage system Improved. | 40,500 | 2009 |
Galway County Council | Carrowmore Woodlawn | To install new piped drainage system to replace existing stone & undersized culvert. | 36,000 | 2019 |
Galway County Council | Derrymullan Ballinasloe | Derrymullen Flood Defence Additional Works-The diversion of an existing open drain / Deepening & widening of the Deerpark River / Provision of a second culvert at Ahascragh Road. Construction of a flood defence wall | 108,000 | 2011 |
Meath County Council | Woodtown | Provide a new separate culvert to cater for flood conditions independent of the existing Road Drainage | 61,200 | 2016 |
Tipperary County Council | Nenagh Swimming Pool & Adjacent Land | Clean drains/stream of silt/debris/vegetation Upgrade embankments | 13,500 | 2012 |
Galway County Council | Moylough Ballinasloe | Maintenance to 1.2km of channel including removal of silt & vegetation | 13,500 | 2019 |
Galway City Council | Two Mile Ditch | Construct pump sump & provide mobile pump. Construct pipeline to existing surface water drainage system. | 27,000 | 2010 |
Offaly County Council | Ballyshane Kinnity | Upgrade culvert | 54,000 | 2010 |
Meath County Council | Northlands Bettystown | Study to identify catchment area flowing into estate & detailed analysis of possible potential solutions | 36,000 | 2012 |
Limerick City & County Council | Cross of Black Kilmallock | Excavation and re profiling of over 1 km of channel/land boundary drains and the replacement of an existing road crossing with a 900 mm dia. pipe | 37,980 | 2020 |
Cork County Council | Bantry, the Quays, Wolfe Tone Square South & New Street | Proposal to provide Flood barriers at each of the 32 no. doors to prevent water entering properties during flood events. | 71,582 | 2024 |
Kerry County Council | Castlemaine Harbour | The consultant shall undertake a site visit, detailed historical review and desk study of all available information relating to coastal erosion/accretion and flooding risk at Dingle Bay East-Castlemaine Harbour. This includes a review of topographic and hydrographic surveys, airborne and terrestrial LiDAR surveys | 2,622 | 2022 |
Kerry County Council | Kenmare Town | Removal of beam / drain under Finnihy Bridge / Installation of gauges / Establish monitoring programme | 99,000 | 2012 |
Galway County Council | Ganaveen Lismanny Laurencetown Ballinasloe | Upgrade existing bridge / Channel improvement works | 14,400 | 2012 |
Cork County Council | Glashaboy River | River cleaning works only to improve hydraulic capacity | 36,000 | 2012 |
Dun Laoghaire / Rathdown | Johnstown / Granville Road | Study, upgrade of trash screen, access road realignment & replace section of boundary fence | 30,000 | 2016 |
Galway County Council | Caherpeak | Relay new pipe | 31,500 | 2012 |
Louth County Council | Annagassan | Construction of rock armour revetment | 10,800 | 2015 |
Limerick City & County Council | Ballynamona Askeaton | Construct a 375m storm water drainage main (450mm diameter) along the public roadway and along private lands to outfall to OPW AD | 63,225 | 2020 |
Galway County Council | Carraroe Area Office, Inverin | Install new culvert under road | 5,850 | 2010 |
Galway County Council | Ballinakill Loughrea | To replace the existing culvert system with circa 90m of 750mm diameter storm water culvert & associated works | 45,000 | 2017 |
Kerry County Council | Ballyheigue Cliff Stabilisation | The scheme is designed to stabilise a 50m length of the Ballyheigue coastline that was suffering sever erosion and was in imminent risk of causing the undermining Head Road. The works involved stabilising this section consisted of the construction of a new concrete anchor block including ground anchorages the importation and placement of suitable rock armour type fill material the provision of geotextile layers, the provision of gabion mattressing and the top soiling of stabilised area. | 106,037 | 2024 |
Galway County Council | Fahy's Grannagh | Construct a 40m length of reinforced concrete retaining wall, 1.2m high around a section of the farmyard | 5,400 | 2016 |
Galway County Council | Feagh East Abbeyknockmoy | Construct / replace three road crossings, supply and lay 570m of 600mm pipe, open new drain & associated works | 71,685 | 2018 |
Galway County Council | Ballyglunin | Channel widening, upgrading culverts | 60,000 | 2010 |
Tipperary County Council | Ballinahalla Clogheen | To install drainage gullies & lay approximately 800m of 300mm diameter storm water drainage pipe to outfall | 45,000 | 2016 |
Monaghan County Council | Kibberidog | Upgrade the existing stone masonry bridge & 450mm pipe to new 1500mm x 1500mm box culvert | 54,000 | 2018 |
Tipperary County Council | Greenan Templederry | Removal of existing boundary wall at the affected property including the sections collapsed. Excavation of silt deposits under bridge arch no. 1 to increase the headroom. Importation and compaction of 6-12" rock to restored river bed. Deposition/relocation of existing river bed material. Placing of Rock Armour and creation of earth retaining bund. Placing of Suitable fill material behind rock armour. | 31,613 | 2024 |
Galway County Council | Skecoor Kiltormer | Clean existing open drains, replace 300mm diameter surface water pipeline with a 450mm pipeline. Filter drainage to be provided for a distance of approximately 75m | 33,030 | 2018 |
Cavan County Council | Butlersbridge | Upgrade culvert / Install flap valve at mouth of pipe entering river. Clean drains in the vicinity & repair roadway. | 38,700 | 2012 |
Galway County Council | Farnaun Peterswell | Increase capacity to bridge and clean stream of vegetation & silt | 18,000 | 2020 |
Limerick City & County Council | Spittle, Ballylanders | Proposed channel clearance of excess vegetation and silt build up over a length of approx. 2km of existing watercourse plus reinstating the channel bed invert level to existing levels to restore/maximise the channel conveyance capacity within the watercourse and installation of 450mm dia. pipe over an approximate length of 260m to improve surface water drainage. | 45,000 | 2022 |
Leitrim County Council | Dromahair - River Bonet | Feasibility Study | 18,000 | 2021 |
Kerry County Council | North Kerry Way National Trail Seawall (coastal) | Repairs to an existing seawall between The Spa & Cockleshell Road, Tralee | 18,124 | 2018 |
Tipperary County Council | Knockballiniry Goatenbridge | Excavation works, the laying of 450mm diameter corripipe, two road crossings & associated works | 32,625 | 2017 |
Offaly County Council | Newtown to Ballybritt | Install 1m pipes & associated works | 29,444 | 2019 |
Galway County Council | Killevny Laurencetown | Open culverts under bridge and construct channel | 4,050 | 2010 |
Donegal County Council | Ecclesiastical Graveyard Inver Glebe | Installation of 60m rock armour along the Eany Water River bank to protect the old graveyard and ecclesiastical remains | 13,500 | 2016 |
Kerry County Council | Cullavaw River Rathmore | Removal of instream gravel & silt build-up at various locations either side of the 3 no. road bridges along the Cullavaw River | 4,500 | 2015 |
Galway County Council | Poolboy Ballinasloe | Upgrade culvert | 19,800 | 2010 |
Galway County Council | Derrymullan Ballinasloe | Provide flood defence wall around the water plant | 45,200 | 2010 |
Tipperary County Council | Grange Village Clonmel | Survey and study | 6,300 | 2011 |
Meath County Council | Cortown | Piping from affected area to local stream | 18,000 | 2012 |
Roscommon County Council | Elphin | Hydrometric Study | 9,000 | 2010 |
Waterford City & County Council | Tallow Bridge | Survey & works to clear restrictions at eye of bridge. Repairs to river bank | 22,500 | 2017 |
Cork County Council | Kilmacahill Cloyne | Replacement of culverts and works to watercourses | 8,100 | 2012 |
Galway County Council | Tierney's Yard Oughterard | Install 170m of 600mm diameter surface water drain, two manholes & a petrol interceptor | 27,922 | 2018 |
Mayo County Council | Crossmolina Chapel Street | To reconstruct part of the existing stone wall | 12,207 | 2017 |
Galway County Council | Shanagalish Gort | Clear swallow hole / Construct 1.4km drainage channel / Associated works | 72,000 | 2012 |
Wexford County Council | Gorey | Bridge improvements, channel cleaning & regrading | 450,000 | 2010 |
Longford County Council | Ballymulvey Ballymahon | Channel cleaning works (550m) | 46,332 | 2016 |
Kerry County Council | Dingle Bay East- Castlemaine Harbour | Coastal Erosion & Flood Risk Management Study | 75,000 | 2018 |
Leitrim County Council | Glenfarne | General channel maintenance & provision of fencing Removal of blockages in river / Clearance of tributary of trees and debris downstream of Road Bridge (add to 2010/11 allocations) | 90,000 | 2010 |
Clare County Council | Whitestrand, Miltown Malbay | Detailed design and planning | 36,000 | 2020 |
Offaly County Council | Derrynagun Lamonaghan | To construct an earthen embankment to contain flood waters from a channel leading to the River Brosna | 8,211 | 2018 |
Wicklow County Council | The Murrough | Coastal erosion rock revetment works | 315,000 | 2016 |
Mayo County Council | Crossmolina Chapel Street | To repoint/repair existing stone wall | 29,700 | 2016 |
Louth County Council | Blackrock | Works – Repair to sea walls | 31,500 | 2009 |
Kerry County Council | Cromane | Embankment strengthening works | 100,000 | 2012 |
Roscommon County Council | Ballyglass River Dysrt | Study | 7,000 | 2009 |
Leitrim County Council | Mountcampbell | Remove trees from river and remove all timber | 27,000 | 2011 |
Galway County Council | Caltragh Laurencetown Ballinasloe | Replacement of bridge | 10,800 | 2012 |
Mayo County Council | Tullinacurra | Works – construct drain | 20,000 | 2009 |
Tipperary County Council | Barravie | Construct gullies and lay piping, upgrade existing pipe, clean out existing land drain | 18,054 | 2010 |
Galway County Council | L42196 Roo Craughwell | To construct a new 450mm diameter storm water collection system & associated works | 17,100 | 2018 |
Westmeath County Council | Brookfield | Works-Construct new culvert under road at B847 | 45,000 | 2009 |
Monaghan County Council | Lisnagunnion | Study | 8,000 | 2012 |
Galway County Council | Carheenlea Turloughmore | To carry out exploratory works, CCTV & a level survey of the existing pipe | 4,500 | 2012 |
Tipperary County Council | Red City Fethard | Upgrade culvert | 52,920 | 2010 |
Carlow County Council | Fonthill Ballinabrannagh | Install flood gates at pedestrian, vehicular & field gate entrances and openings on opposite side of public road. Provide sump to facilitate over pumping of surface waters & construct buttress wall to rear of wall of property | 14,760 | 2016 |
Galway County Council | Kiltiernan to Ballinderreen | Main drainage works & additional pipe-laying works on the Kiltiernan channel | 247,870 | 2015 |
Sligo County Council | Rosses Point | Installation of 34m of rock revetment to protect the public path | 124,200 | 2021 |
Mayo County Council | Tonrehown | Construct new wall | 10,000 | 2009 |
Galway County Council | Garrymore Ballymacward Ballinasloe | Replace existing culvert with culvert of larger capacity & regrade existing open drains | 16,200 | 2011 |
Galway County Council | Feagh East | Open up swallow hole, place grids on roadside | 3,000 | 2010 |
Laois County Council | Stradbally | Repoint walls, culvert works, fit a non-return value | 14,400 | 2010 |
Tipperary County Council | Grange Road Ballina | To provide 12 inch diameter SW piping and associated road gullies for a total distance of 400m | 47,610 | 2011 |
Tipperary County Council | Mullinahone | Removal of debris from the channel and banks prior to building a foundation and retaining wall along the banks A design and method statement to be developed | 225,000 | 2017 |
Galway County Council | Kilcoona | Install a new 450mm piped culvert across the road | 4,500 | 2010 |
Carlow County Council | Carriglead Lock House | Install flood barriers, construct ramp and sump & associated works | 10,125 | 2017 |
Kilkenny County Council | Graignamanagh (River Duiske) | Removal of build up of silt and debris from the river channel through to the centre of town | 36,000 | 2011 |
Tipperary County Council | Ardfinnan Clonmel | Works – Strengthening riverbank, raising embankment & removal of vegetation. | 162,684 | 2009 |
Longford County Council | Tureen/ Lismacmaunus | Clean land drains over 2kms and repair old/blocked stone culverts | 21,600 | 2016 |
Galway County Council | Knockanranny | Replace partially collapsed culvert with a 900mm pipe | 10,800 | 2010 |
Galway County Council | Ballyconlought Headford | Piping of channel | 23,000 | 2010 |
Galway County Council | Lydican Cregboy | Improve drainage | 13,500 | 2010 |
Roscommon County Council | Knockalgtha | Study | 2,070 | 2010 |
Roscommon County Council | Cloughan Four Roads | Installation of culvert and open drain | 16,200 | 2011 |
Kilkenny County Council | Clogh | Construction of embankment / Channel widening and maintenance | 65,000 | 2010 |
Galway County Council | Crowe St. Gort | Channel maintenance and camera survey | 32,400 | 2011 |
Roscommon County Council | Ballyglass River Dysrt | Study | 3,987 | 2010 |
Galway County Council | The Rossaveel Sportsgrounds | Re-grading and cleaning of the stream & existing drainage system. | 9,000 | 2021 |
Limerick City & County Council | Bresheen South Kilmallock | To replace existing concrete pipe culverts with box culverts of significantly larger cross sectional area of 3.6m wide x 1.8 high, 2 parapet walls & associated works To construct 50m of linear drainage channel | 45,720 | 2021 |
Galway County Council | Cloonamore- Inishboffin Island as a whole | Comprehensive coastal erosion & flood risk management study for Inisboffin Island as a whole | 90,000 | 2015 |
Wicklow County Council | Rathbran Grangecon | Remove and dispose of 25metres of concrete surface water pipes & restore 25metres of the channel to it's original width, depth and capacity | 4,050 | 2016 |
Galway City Council | Clare River Galway City | Carry out tree cutting & vegetation removal, masonry repairs, culvert repairs & silt removal | 61,650 | 2019 |
Roscommon County Council | Crancam Athlone | Install 600mm perforated drainage pipe in road/verge for distance of 300m and connect existing water drain to it, clean local drain & associated works | 108,207 | 2019 |
Galway County Council | Peterswell Gort | Replace existing culverts & maintain existing open drains | 22,500 | 2012 |
Galway County Council | Crowsnest Laurencetown | Upgrade culverts | 9,000 | 2010 |
Galway County Council | Inchaboy South Gort | Lowering of culvert. Reinstate road surface and lands | 14,400 | 2012 |
Galway County Council | Clonbern Tuam | Regrading of agricultural lands to divert flow path of floodwaters | 18,000 | 2018 |
Mayo County Council | Devlin North | Works - Repair bridge & channel | 36,000 | 2009 |
Kerry County Council | Kinard, Lispole | Stabilisation of the existing slope by soil nailing and shot creteing the cliff face. In addition, the surface water drainage networks in the vicinity of the proposed works to be altered | 56,796 | 2021 |
Galway County Council | Ahascragh | Channel cleaning | 45,000 | 2010 |
Roscommon County Council | Grange | Study to determine possible alleviation measures | 1,800 | 2010 |
Leitrim County Council | Greyfield | Channel Cleaning General channel maintenance and provision of fencing | 28,000 | 2010 |
Roscommon County Council | Highbog Rahara | Drainage system Improved | 31,500 | 2009 |
Roscommon County Council | Cullawinnia | Install new pipe culverts & clean open drain | 29,250 | 2011 |
Mayo County Council | Newport | Replace ditch with box culvert /Clean, repair and remove debris from rest of drainage system | 180,000 | 2010 |
Tipperary County Council | Moangarriff Clonmel | Channel improvements | 30,600 | 2010 |
Tipperary County Council | Ardfinnan Clonmel | Works – Strengthening riverbank, raising embankment & removal of vegetation. | 44,550 | 2010 |
Kildare County Council | Sallins | Culvert upgrade, embankment | 500,000 | 2010 |
Laois County Council | Shannon Rd Mountrath | To install a new culvert at a higher invert level to the existing culvert | 46,565 | 2020 |
Mayo County Council | Derryguillinan Cloghans | Install new culvert under road | 31,500 | 2010 |
Cork County Council | Garranachole Castletownroche | Installation of gully trap and perforated drainage pipes & associated works | 22,500 | 2021 |
Cork County Council | Crookstown | Storm water pumping station, new drainage pipes & associated works | 295,027 | 2021 |
Louth County Council | Blackrock Sea Wall | To repair the revetment & associated works | 27,000 | 2013 |
Kerry County Council | Milltown Village | Study | 2,700 | 2010 |
Kilkenny County Council | Ardaloo, Jenkinstown | Flood Study/ Flood Risk Assessment of the area outlined | 54,000 | 2022 |
Kerry County Council | Goulane-Maherees | Clean silt and sand from rivers and estuaries | 9,000 | 2009 |
Carlow County Council | Burrin Bridge | Removal of deposited silt from a section of the river from Burrin Bridge to downstream to the confluence with the River Barrow. | 20,700 | 2017 |
Galway County Council | Turloughgarve Corrandulla | Install culvert and construct new drain | 16,200 | 2010 |
Donegal County Council | Sloddan Port to Binbane Head (to include Pollan Strand, Ballyliffin & Five Fingers Strand) | Coastal Erosion Risk Management Study | 76,500 | 2016 |
Roscommon County Council | Killukin River Carrowreagh | Study Only | 7,000 | 2009 |
Carlow County Council | Tullow | Construction\installation of walls, berms, flood gates along River Slaney / Upgrade drainage system along Thom Traynor Road / Installation of pumps and sumps | 100,000 | 2012 |
Offaly County Council | Ballymooney & Ballyknockan, Geashill | Upgrade culvert | 90,000 | 2010 |
Tipperary County Council | Gortnahoola, Drombane, Thurles - Revised | Construct a new 750mm surface water storm line 155 metres along public road | 29,700 | 2023 |
Limerick City & County Council | Condell Road Limerick City | Strengthening, widening & raising to a level of 4.46 metres O.D. (Malin) 600 metres section of embankment | 90,000 | 2016 |
Galway County Council | Knocktogher Kiltullagh | To carry out channel maintenance works upstream & downstream of the existing culvert along with increasing the capacity of the culvert via de-silting works | 14,045 | 2015 |
Roscommon County Council | Fairhill Dysart | Works to raise the ground level and install piping | 18,000 | 2016 |
Galway County Council | Ferragh Caherlistrane | Improvements to Corrib Clare Arterial Drainage Scheme | 115,000 | 2010 |
Galway County Council | Carrownamorrissy, Craughwell | Galway County Council are to install a surface water collection system on the R348 with a number of gullies and manholes. This system will bring the flood waters to an existing open drain 300m to the north which out falls to the Dooyertha River and the proposed works are to link the piped section to the culvert via a new shallow open drain. The existing culvert is to be upgraded to a 900mm diameter pipe. | 18,000 | 2024 |
Leitrim County Council | Stonepark Dromahair | Construction of embankment between Bonet River and R289 | 22,300 | 2012 |
Galway County Council | Gortaha Portumna | Replace existing culvert with larger 450mm diameter pipe | 16,875 | 2018 |
Meath County Council | Delvin River Stamullen Athena | Meath County Council report that flooding arises at residential properties at Gormanston Road, Stamullen. The river Delvin runs close to the rear of these houses and the strip of land between the river and the rear gardens of the houses is a flood plain. The rear gardens of these three houses regularly flood. Meath County Council have proposed to have the area assessed by a suitably qualified and experienced consulting Engineer ( involving necessary hydrological and investigative works) This will determine the cause/s of the flooding and identify / recommend the required solution/s. | 45,000 | 2025 |
Dun Laoghaire / Rathdown | Monkstown | Monkstown & Stradbrook Stream hydraulic assessment study | 135,000 | 2020 |
Kilkenny County Council | Ballyfoyle Road | Construction of new culvert across Ballyfoyle Road / Construction of new culvert in private garden by trenchless technology / Clean open channel and other culverted sections of the stream | 63,000 | 2013 |
Galway County Council | Cloonantleva Lower Fohenagh | Replacement of culverts | 18,000 | 2010 |
Galway County Council | Cross St/Lake Road Loughrea | Installation of additional gullies / removal of existing culvert & replacement with a culvert of greater capacity | 67,500 | 2010 |
Tipperary County Council | Marlfield Clonmel | Tipperary County Council propose to install temporary works to support the large retaining wall and parapet, if deemed necessary; Remove all vegetation and trees within the vicinity of the culvert. TTC propose to partly remove and strengthen the existing stone masonry and concrete retaining walls to the upstream embankments. | 45,000 | 2024 |
Galway County Council | Moneen, Cummer, Tuam | Install 600mm pipe | 9,900 | 2010 |
Galway County Council | Crowe Street Gort | Channel Maintenance | 38,000 | 2010 |
Longford County Council | Parnell Rd Granard | To upgrade culverts and channel | 73,110 | 2011 |
Cork County Council | Bandon River Bandon Town | Tree Cutting | 27,000 | 2011 |
Galway County Council | Atticora Creagh Ballinasloe | Install a new 450mm diameter surface water pipe for distance of 250m to an existing drain & associated works | 14,940 | 2017 |
Wicklow County Council | Arklow Town | Coastal Protection Study | 81,000 | 2010 |
Roscommon County Council | Ballymurry South | Install 750m of 900mm diameter pipework 450m in hard shoulder of N61 from flood location & 350m inland connecting to existing land drain. One road crossing required | 54,000 | 2017 |
Galway County Council | Knockatee East Dunmore | To drain flooded area to nearest outfall, comprising 150m of 12'' perforated pipe | 10,800 | 2013 |
Cork County Council | Inchigeelagh | Selectively clear bank side trees & shrubs Clear river bed material | 22,500 | 2016 |
Waterford City & County Council | Lacken Bridge Rathgormack | Prune riverside trees. Re-shape riverbanks. Remove deposits at bridge eyes | 13,500 | 2010 |
Roscommon County Council | Strokestown | Study of Stokestown River Catchement | 18,000 | 2010 |
Galway County Council | Crowes Spiddal | Regrading of stream / Upgrade culvert | 13,500 | 2012 |
Longford County Council | Lisnacush Lanesboro | Improve / drain the land drainage over 1.0kms, install a 900mm diameter pipe at 1-2 crossings to improve flow of water | 31,500 | 2017 |
Roscommon County Council | Taghboy Ballyforan | Drainage system Improved. | 18,900 | 2009 |
Galway County Council | Rosmore Woodford | Construct a new 600mm diameter storm water collection system & associated works | 23,400 | 2018 |
Clare County Council | Kilkee Sea Wall | Underpinning for additional area of poor foundations on the Seawall | 8,123 | 2022 |
Limerick City & County Council | Broadford (R515) | Construct storm sewer, provide and connect gullies | 23,985 | 2010 |
Galway County Council | Kilglass Ahascragh Ballinasloe | To install 270m of 450mm diameter SW carrier sewer, 180m of cleaning of existing open drain & 6 no. manhole gratings | 38,250 | 2019 |
Galway County Council | Cregboy | Installation of flood gates | 10,800 | 2020 |
Kerry County Council | Fenit Road | Fenit Road Coastal Protection Scheme – Rock revetment & buttressing embankments | 405,000 | 2010 |
Galway County Council | Kilconnell | Lay a new culvert along the route of the stone shore drainage system | 36,000 | 2009 |
Galway County Council | Cloonatleva Ballymacward | To direct flood water to lower lands | 5,220 | 2013 |
Galway County Council | Inisboffin-South Shore | New coastal protection barrier- in form of wall constructed from integrated PC block elements- as detailed in RPS report 2014 & being used for new or repair of existing damaged sections of walls at Southern Shore | 441,900 | 2015 |
Kilkenny County Council | Thomastown | Site investigation | 40,000 | 2010 |
Donegal County Council | Foxwood | Clear vegetation for approximately 850m Minor widening of river & sweetening of corners for approximately 850m Increase height of embankment behind houses | 18,000 | 2014 |
Donegal County Council | Burnfoot River | Construct earthen embankment / Investigate underground drainage & upgrade where required | 67,500 | 2010 |
Galway County Council | Lacka 2 Bridge | Replace existing bridge with a new larger structure with a greater hydraulic capacity | 27,400 | 2012 |
Kildare County Council | Butterstream Clane | Construction of flood relief structures | 356,142 | 2010 |
Longford County Council | Garrynagh Ballymahon | Clean/dredge open land drains from Moigh Road to River Inny | 10,800 | 2015 |
Galway County Council | Kiltiernan to Ballinderreen | Main drainage works & additional pipe-laying works on the Kiltiernan channel | 194,680 | 2019 |
Wexford County Council | Seaview Kilmore Bastardstown | Wexford County Council propose to implement 155m of rock armour coastal protection fronting several houses at Seaview (Bastardstown) on the Wexford Coast. Emergency works were undertaken to the initial 100m of coastline (section 01). WCC intend to implement an additional layer of rock armour in order to bring emergency works up to long term standard. WCC will then add additional full rock armour to the second section (section 02) for next 55m of coastline. The proposed works in this application directly protect some 10 of these houses and some 155m the access road. | 668,921 | 2024 |
Galway County Council | Thornfield Portumna | Widen & deepen existing open channel / Open new section / Clear existing roadside channels / Install new culvert across N65 / Undertake reinstatement works | 47,250 | 2010 |
Galway County Council | Derrydonnell Oranmore | Channel maintenance, pipes, replacement of culverts | 300,000 | 2010 |
Louth County Council | Carlingford Promenade Sea Wall | To repair the revetment & associated works | 9,990 | 2013 |
Kerry County Council | Tralee | The removal of debris, deposition & sediment under bridges and weir & associated works. Structural survey & inspection of bypass culverts. | 44,396 | 2015 |
Tipperary County Council | Ardfinnan Clonmel | Installation of 40 linear metres by approx 3 metres height of rock armour to provide 1.2 metres height of protection to existing river bank | 15,480 | 2010 |
Louth County Council | Townparks Dundalk | Extend an existing 1350mm diameter drainage pipe towards Balmer’s Bog & associated works | 668,571 | 2019 |
Clare County Council | Cloughauninchy | Appointment of consultants for detailed design and planning | 36,000 | 2017 |
Louth County Council | Baltray | Construct/raise embankment wall | 18,000 | 2009 |
Galway City Council | Sruffaunacashlaun Stream && Distillery Canal | Channel maintenance on the open channel section of the stream & trash screen replacements, Carry out desilting works on Distillery Channel, Tree cutting & vegetation clearing works, Prepare AA screenings, assessments & reports | 163,800 | 2023 |
Clare County Council | Ballyvaughan | New pipe from turlough to the sea | 270,000 | 2011 |
Kerry County Council | Ballyard | Works – Remove silt and accumulated stone from river & install additional drainage culvert. | 13,500 | 2009 |
Limerick City & County Council | Groody River Ballysimon | Replace the weir that was carried away in the flooding event in February 2017 | 36,000 | 2018 |
Kilkenny County Council | Callan | Silt Mounds to be assessed and on-going issues with the current pumping arrangement that needs to be future proofed following recent flood events in Callan in Oct 2022 | 18,000 | 2022 |
Cavan County Council | Drumcliff Ballyhaise | To re-construct existing culvert 65m long 600mm diameter | 17,100 | 2020 |
Cork County Council | Coachford Village | Culverts are old, under capacity and sections are in bad repair. Study required to investigate the flooding mechanisms, improve capacity and what remedial works are needed to the existing culverts | 36,000 | 2023 |
Galway County Council | Cooleran Turloughmore | Dig 240m open drain (remove trees and ditch) Lay culvert & 90m of pipe to drain (900mm diameter) & associated works | 34,650 | 2017 |
Cavan County Council | L6027 Ballyhaise Pitch | To construct an overflow either full length of field or option 2 to construct an overflow culvert under link between pitches discharging into a newly constructed open overflow field drain | 14,850 | 2020 |
Tipperary County Council | Ardfinnan | Replace old Barriers with a modern reliable new system that is fit for purpose | 27,000 | 2024 |
Mayo County Council | Ballyhankeen Claremorris | Deepen existing drains & excavate short length of new open drains & upgrade culverts | 56,765 | 2017 |
Donegal County Council | Ranamona Island Causeway | To re-set & rebuild existing boulders and import replacement boulders | 10,800 | 2019 |
Leitrim County Council | Bonet River Dromahair | Feasibility Study | 12,122 | 2022 |
Limerick City & County Council | Castleconnell | Flood study / Construction of impermeable earthen embankment & associated works at rear of Meadow Brooke estate/ Purchase of temporary booms & pumps /Placement of a sluice onto the bridge culvert at the Island House. | 63,000 | 2010 |
Wexford County Council | Old Town Lane Castlebridge | Replacement of existing 600mm diameter pipes with 1200mm pipes, terminating in a pumping chamber under the roadway. | 61,200 | 2010 |
Cork County Council | Bantry Interim Works | Additional funding for works- mobile pumps, sump chambers, sealing gullies, non-return valves, large sandbags & associated works | 82,339 | 2022 |
Limerick City & County Council | Foynes | Appointment of consultants to survey the existing defences and to prepare a detailed design of proposed improvements to include costings and a Cost Benefit Analysis. | 45,000 | 2014 |
Fingal County Council | R127, Skerries Balbriggan Regional Road | Emergency sea defence works- stonework pointing, replacement of existing wall, additional rock armour & re-instatement of damaged rock armour | 197,480 | 2014 |
Offaly County Council | Portavolla Estate Banagher | To construct a clay embankment of approximate height of 1.0-1.2m around the perimeter of the Portavolla Estate to a total length of approximately 470m. Scope of works also includes the diversion of an existing drain from the rear of the houses to outside of the new bund. Facility to over pump during a flood event to be installed | 153,000 | 2016 |
Limerick City & County Council | Atlas Avenue off Dock Road | Installation of a hinged access gate, construction of an RC wall to tie in with existing embankments & associated works. | 57,600 | 2019 |
Leitrim County Council | Leitrim Village | Construct a containment structure with a headwall & a removal weir (including pumps) on the south west side of road. | 45,000 | 2014 |
Monaghan County Council | Threemilehouse Village | Clean section of open stream, clean & repair road culvert, increase height of headwalls, replace pipes, repair & strengthen stone and concrete banks & install additional roadside drainage | 135,000 | 2013 |
South Dublin County Council | Owendoher River | Increase the height of the existing reinforced concrete wing/wall Continue this reinforced concrete retaining wall up the banks of the Owendoher River | 43,650 | 2013 |
Wicklow County Council | Avoca (White Bridge) | Removal of a deposit in the Avoca river & use the material to raise the level of the adjacent river bank to form a flood barrier | 8,100 | 2013 |
Leitrim County Council | Glenfarne | General channel maintenance & provision of fencing Removal of blockages in river / Clearance of tributary of trees and debris downstream of Road Bridge (add to 2010/11 allocations) | 15,000 | 2012 |
South Dublin County Council | Tallaght / Jobstown Areas | Redesign and replacement of three significant screens on Jobstown Stream, Killinarden Stream / N81 and at the Jobstown Road. Building of a swale and increase of boundary wall height by 500mm at Knockmore Park and Avenue Installation of two new screens and headwalls at the N81 at Deselby Stream maintenance between Hazelgrove Golf and Jobstown Inn | 333,000 | 2012 |
Clare County Council | Liscannor Bay (Clahane, Liscannor & Miltown Malbay) | Coastal erosion & flood risk management study | 108,000 | 2015 |
Clare County Council | Quilty to Miltown Malbay (Quilty, Spanish Point & Whitestrand) | Coastal erosion & flood risk management study | 65,000 | 2015 |
Wicklow County Council | R762 Delgany | Lay 230m of 12” UPVC SW Line / Reinstatement of road / Construction of manholes /Install gullies / Connect existing gulliesInstall new pipe line | 40,000 | 2012 |
Fingal County Council | Rowlestown | Construction of a flood defence embankment along the left bank of the Broadmeadow Tributary in Rowelstown | 153,000 | 2011 |
Galway County Council | East Bridge Ballinasloe | Provide a channel downstream to the Suck.Engagement of consultant to undertake conservation impact statement / Removal / modification of sluice gates | 40,500 | 2010 |
Galway County Council | N18 at Oranmore | Cleaning of all blockages and obstructions to flow of the stream from N18 to the outfall at the sea | 14,400 | 2010 |
Wicklow County Council | Baltinglass Town Centre | Engagement of consultant to identify feasible measures to address flooding in Baltinglass Town Centre and implementation of said measures / Anticipated works: Dredging of River Slaney / Installation of flap valves on all surface water discharge outlets to the river in the vicinity of Slaney Mall / Flood gating at the Bridge slip-way and at Church Lane | 70,200 | 2010 |
Donegal County Council | Stranorlar-Ballybofey | Construction of pump, 2 storm water manholes & associated works | 101,865 | 2021 |
Donegal County Council | Murvagh Upper Glebe, Drumchory Glebe Mullanacross and Ballybulgan | To undertake a review of the existing flood data to identify measures that could be implemented, to mitigate against future flooding of this area | 13,500 | 2018 |
Limerick City & County Council | Portnard, Cappamore, L5025 | Lay 80m of 225mm drainage Pipe Carry out 1 Road-crossing Installation of 6 Gullies and sumps Installation of 2 Manholes and chambers Re-profiling of existing entrance | 18,900 | 2022 |
Galway County Council | Oranmore to Kinvarra Coastline | Galway County Council (GCC) will conduct a study to identify houses and businesses at risk from the Coastline of Oranmore to Kinvarra. The study is designed to confirm appropriate protection levels required and if properties are defendable under a scheme or IPP measures. GCC will complete a study of the Storm Debi event, including an examination of all data available from OPW river gauges, Marine Institute gauges, coastal gauges, photos and CCTV recordings (gathered post event by GCC). | 108,000 | 2024 |
Longford County Council | Soran Ballinalee | Study and preparing the pre-feasibility screening report, preparing the Section 50 submission for OPW and if successful through to designing the scheme, tendering and carrying out site supervision. Including channel maintenance and bank stabilisation. | 31,500 | 2020 |
Limerick City & County Council | Ballycullen Askeaton | Removal of 2 concrete pipes & 1 concrete pipework with a replacement with new precast culverts over an 8m length with associated works on private grounds | 55,800 | 2017 |
Kerry County Council | Incheree | Construct new embankment of approximately 360m & access road, pipe open drains and culvert Associated works | 8,237 | 2018 |
Limerick City & County Council | Naughton, Ballinatona, Galbally | Clear & remove approx. 3km scrub and organic material from a field drainage pipe & to construct a 90m drainage pipe- 300mm diameter | 25,380 | 2021 |
Galway County Council | Mountbellew Lake Ballinasloe | Galway County Council proposes to engage specialist engineering consultants to survey the section of damaged embankment and sluice gate and provide detailed design for embankment reconstruction and sluice gate repair. It should be noted that it is likely that the damaged/failed earthen embankment section, will continue to experience further failures, without intervention. The works are also to include an environmental impact assessment and any mitigation measure which may be required. Proposals should also consider inclusion of fish pass barrier removal and the sluice gate. | 135,000 | 2024 |
Kerry County Council | Caherleheen | Works – Widen culvert to Caherheen Bridge & incorporate river flow improvements. | 27,000 | 2009 |
Galway County Council | Caheroyn Avenue Athenry | Construct reinforced concrete wall, construct sump, remove existing fencing & walls along river & associated works | 40,500 | 2017 |
Cork County Council | St. Colum’s Community Hall Ballylickey | Construct flood defence wall around the community hall, including slot in flood barriers at access points | 18,000 | 2017 |
Sligo County Council | Carrownagark Kilmorgan | Construct a 110m blockwork wall including two pedestrian flood barriers, two pedestrian gates and entrances | 22,635 | 2020 |
Carlow County Council | Tinnahinch | Provision of flood barriers /Provision of small sump and portable pump / Laying of surface water pipeline and associated works. | 53,550 | 2011 |
Galway County Council | Palmerstown/Derrydonnell North | Excavation of new drain from public road to adjacent Turlough | 4,725 | 2010 |
Clare County Council | Ruan | Flood mitigation works | 90,000 | 2010 |
Limerick City & County Council | Foynes Yacht Club Foynes | Appointment of consultants to survey the existing defences & the appointment of contractors to carry out the works- additional funding | 38,475 | 2021 |
Wexford County Council | Donaghmore Graveyard | Coastal flood defence works, comprising the placing of rock armour at the base of the cliff & the removal of three damaged structures from the top of the cliff | 254,078 | 2016 |
Wexford County Council | Growtown Upper, Taghmon, Barntown, | Remove the existing wall in front of the house, construct new solid block wall removing the pedestrian and vehicle access from the front of the property. Provide new pedestrian access from the local road above flood line of the house. Provide sump pump location at low point in yard to allow surface water to be removed from behind the wall. Divert surface water at the back of the house away from the front of the house | 30,742 | 2024 |
Galway County Council | Ardmore Kilkieran | Increase capacity instream by widening instream for 150m | 18,000 | 2019 |
Galway County Council | The Walks Station Road Loughrea | Clean river & remove debris. Repair damaged crossings if applicable | 27,000 | 2010 |
Kilkenny County Council | Callan (IPP) | The flooding occurred at the three following locations; Kcat Carpark/Keoghs Lane, Bridge Street, and Fennelly’s Café which will require three separate mechanisms for each location. Kilkenny County Council propose to adopt ‘option 2’ detailed in Kilgallens report which will involve implementing a new pumping facility at Kcat Carpark and construct a 900mm diameter overflow pipe. For Bridge Street KCC propose to install a chamber at the lowest point of the surface water drainage system that will permit the use of an emergency pump by Local Authority staff. Surcharging water will be pumped from this chamber to the King’s River; KCC also propose to install IPP for the 8 properties effected. In relation to Fennelly’s café the primary cause of flood risk is the back-up from King’s River when water levels are high. KCC are to address by the installation of a chamber on the existing gravity outfall pipe in the open space adjoining the river, with a flap valve on the inlet pipe to this chamber, thus preventing back flow from King’s River. | 124,540 | 2024 |
Wexford County Council | Wexford Racecourse | Flood alleviation scheme- enlarge an existing irrigation pond & construct an embankment to impound the flood water and restrict the discharge to a lower volume in keeping with the estimated capacity of the network | 99,000 | 2019 |
Monaghan County Council | Shambles River Monaghan Town | To construct a new box culvert across the N54 & the R162 in Monaghan Town, additional flood alleviation measures for the Castle Road area. | 500,000 | 2019 |
Sligo County Council | Breeogue | Install a new stormwater pipeline | 23,252 | 2018 |
Westmeath County Council | Annagh Maghera | To raise road by 1000mm for 100m on existing road to tie into OPW raised embankments to keep road open during extreme events & thus two homes will have access | 36,872 | 2016 |
Leitrim County Council | Leitrim Village | Construct a containment structure with a headwall and a removal weir (including pumps) on the south west side of road. | 213,191 | 2023 |
Carlow County Council | Tinnahinch Quay | Raise level by 350mm for a distance of 80m downstream of Graignamanagh Bridge, provide demountable flood gate to isolate area from flooding from Mill Race, provide demountable flood gates to each of the properties and provide 350mm up stand to existing wall along Mill Race for 20m | 12,780 | 2017 |
Kilkenny County Council | Ardaloo, Jenkinstown, Co. Kilkenny | Kilkenny County Council are proposing to carry out Option 1 as detailed in the report 3 Site Specific Flood Risk Assessment. This option considers using a flood wall around the subject property site. | 78,453 | 2024 |
Monaghan County Council | Donaghmoyne | Upsizing of existing bridge crossing at Mannan Golf Club | 85,500 | 2016 |
Mayo County Council | Cong / Drumsheel | Installation of culverts, construct chambers & trash screens & channel improvement works (as outlined in report) | 324,819 | 2017 |
Fingal County Council | Malahide Town Centre | Study | 45,000 | 2014 |
Galway County Council | Killeenadeema Loughrea | To culvert the existing watercourse with a 600mm diameter twin wall pipe & construct a road crossing to a discharge point approx. 500m downstream into an existing drain | 57,817 | 2015 |
Mayo County Council | Rosturk Mallaranny | Clean existing drainage channel adjacent to the road | 4,500 | 2011 |
Limerick City & County Council | Tobernea Kilmallock | Demolish 2 concrete pipe culverts & replace with box culverts of significantly larger cross sectional area. | 40,230 | 2021 |
Galway County Council | Leenaun Graveyard & Parochial House | Rock armour works | 49,500 | 2020 |
Galway County Council | East Bridge Ballinasloe | East Bridge Flood Eyes - Consultant fees for design, procurement of works and land acquisition | 27,000 | 2011 |
Galway County Council | Gortbeg Cahergal Tuam | Improvements to Corrib Clare Arterial Drainage Scheme | 49,000 | 2010 |
Westmeath County Council | Aghanargit Moate | To carry out a survey to determine location and extent of issues & to carry out remedial works on the existing pipeline | 36,450 | 2019 |
Limerick City & County Council | Gardenfield, Monagea | Proposed channel clearance of excess vegetation and silt buildup of 450m, including reinstating the channel bed to original levels | 5,850 | 2022 |
Galway County Council | Glentane Ballinasloe | To replace the existing culvert system with circa 90m of 750mm diameter storm water culvert & associated works | 63,450 | 2017 |
Galway County Council | Parkacurry Monivea | To clean & maintain overgrown sections of the open channel, upsize 1 no. road crossing to a 900mm diameter pipe, install 100m of 225mm diameter surface water drainage pipe & road gullies and provide two new headwalls and trash screens to outfall to existing open channel | 11,700 | 2016 |
Galway County Council | Ballyglass South Ballymore | Drain area to nearest outfall and construct two manholes at this location | 54,000 | 2010 |
Galway County Council | Ballinderry Kilconnell Ballinasloe | Replace existing culvert with culvert of larger capacity & regrade existing open drains | 16,200 | 2011 |
Wexford County Council | Wexford Racecourse | Flood alleviation scheme- enlarge an existing irrigation pond & construct an embankment to impound the flood water and restrict the discharge to a lower volume in keeping with the estimated capacity of the network | 126,000 | 2018 |
Cork County Council | Ballintubber | To complete the laying 940mm of 450mm diameter pipe from the northern boundary of the nursery (Irish Plant Propagation Ltd) to the outfall to existing stream approximately 940m south. | 126,499 | 2022 |
Donegal County Council | Derrybeg | Bunding behind private dwelling | 58,500 | 2010 |
Kerry County Council | Clieveragh Listowel | Site investigation, detailed design, preparation of tender documents & land acquisition | 148,370 | 2017 |
Donegal County Council | Cladyknit | Study | 3,600 | 2010 |
Clare County Council | Gort na Null Sixmilebridge | Raise the level of the current embankment by the construction of an engineered embankment 142m long & to upgrade sluice | 63,129 | 2019 |
Dun Laoghaire / Rathdown | Loreto Park Nutgrove | Install new screen to latest standards | 31,500 | 2016 |
Mayo County Council | Killateeam Tourmakeady | Replacement of culvert | 16,200 | 2012 |
Tipperary County Council | Cloughcarrigeen Estate Kilsheelin | To install new 240m long 300mm diameter surface water drainage pipe, connect existing open channel linear attenuation drain to new estate surface water drainage system & clean existing open drain | 63,000 | 2016 |
Monaghan County Council | Castleshane | Clear 1km of stream | 54,000 | 2009 |
Limerick City & County Council | Bresheen South Kilmallock | Culvert replacement on the R515. | 16,002 | 2022 |
Clare County Council | Rineville Carrigaholt | To infill the existing revetment as detailed in the application | 90,000 | 2018 |
Limerick City & County Council | Newcastle West/ West Limerick | Procure 2 emergency pumps | 99,000 | 2010 |
Cavan County Council | Mullinavanogue Redhills | To re-construct existing culvert 65m long 600mm diameter | 11,700 | 2020 |
Tipperary County Council | Cascade Height Clonmel | Provide side support to the existing banks of Aulk Stream and reinforced concrete wall to front / Purchase concrete blocks and amend grille / Clean culvert under the road | 14,805 | 2010 |
Wicklow County Council | Brittas Bay, Kilpatrick,Ennereilly | Coastal Erosion Risk Management Brittas Bay and Ennereilly, County Wicklow | 121,500 | 2023 |
Kerry County Council | Tullig Castleisland | Raising of retaining wall, culvert replacement at Tullig, storm water drainage pipe at Kilbannivane & associated works | 144,000 | 2014 |
Clare County Council | Kilbaha, Aughinish & New Quay | Coastal erosion & flood risk management study | 102,000 | 2015 |
Donegal County Council | Oatfield Terrace Letterkenny | Removal of structurally damaged pipes & installation of box culvert 3m x 2.1m | 224,460 | 2018 |
Waterford City & County Council | Duckspool Dungarvan | Replacement of current outfall with outfall pipes that are capable of handling the flood flows | 562,050 | 2019 |
Tipperary County Council | R504 at Longhouse Birdhill | Install 4no new gullies & lay 100m of 300mm diameter drainage pipes to an outfall | 13,500 | 2015 |
Kerry County Council | Rossbeigh | Construction of a rock revetment | 450,000 | 2018 |
Clare County Council | Milltown Malbay | Replacement of culvert | 45,000 | 2012 |
Kerry County Council | Dromartin Ballyduff | Construction of a reinforced concrete wall & associated works | 34,311 | 2020 |
Clare County Council | Ballyrine Doolin | Provision of sump & pump | 45,000 | 2012 |
Carlow County Council | Leighlinbridge | Flood alleviation works along banks of River Barrow at Carlow Road (Lord Bagenal Hotel) & Barrow Track (Garrison House), together with ancillary drainage works | 260,010 | 2010 |
Mayo County Council | Copper Beech Straide | Raise embankment at site- 35m embankment 5600 high with slopes 1:1 | 5,490 | 2016 |
Mayo County Council | Crossmolina | Provide two pump sumps to utilise when river levels are elevated and flooding is occurring | 8,190 | 2020 |
Galway County Council | Ardacong Tuam | To lay a pipe to connect to the storm damage 450mm diameter pipe across the road, with manhole, headwall & penstock control to provide a facility to release some flood waters from Ardacong turlough via gravity and/or pumping | 20,633 | 2017 |
Cork County Council | Bantry Interim Works | Works- mobile pumps, sump chambers, sealing gullies, non-return valves, large sandbags & associated works | 101,578 | 2021 |
Leitrim County Council | Rossinver | To carry out a tree management programme & channel improvements over a distance of 4km on the Glenariff River | 38,384 | 2020 |
Limerick City & County Council | Ballymackessy (Monagea) | Construct storm sewer, provide and connect gullies | 29,700 | 2010 |
Roscommon County Council | Ballymurry North | Install 400m of 900mm diameter pipework in hard shoulder of N61 from flood location to existing land drain. Clear 850m of land drain towards River Hind. One road crossing required | 36,000 | 2017 |
Dublin City Council | Camac River at: Carrickfoyle Terrace, Millbrook Terrace & Lady's Lane, Kilmainham | Installation of 60m rock armour along the Eany Water River bank to protect the old graveyard and ecclesiastical remains New early warning device | 225,000 | 2012 |
Carlow County Council | Paupish Lane | Investigation works to determine size, invert & orientation of existing culverts, construction of reinforced concrete chamber, installation of non-return valves in new chamber & associated works | 36,000 | 2014 |
Cavan County Council | Ballyhaise Cavan Road | To create 150m land drainage to rear, install 70m 225 diameter drain to rear to discharge into existing system & renew 100m of 300 diameter culvert downstream of properties | 10,350 | 2020 |
Galway County Council | Knockbane Moycullen | Construction of an earthen embankment & culvert upgrade. | 13,500 | 2021 |
Wexford County Council | Rosslare Spit West Side | The construction of an earthen embankment and sections of demountable wall. Total length 1,075 metres | 551,377 | 2020 |
Leitrim County Council | Dromahair River Bonet Phase2 | Implement Options 4a,b,c,d as identified in the Feasibility Report | 588,420 | 2023 |
Kilkenny County Council | Fahee Kilmacow | Works-Drainage Works and Bridge Replacement | 67,500 | 2009 |
Clare County Council | Roughan | Provide new 750mm pipe Increase embankments around dwelling houses | 99,000 | 2011 |
Galway County Council | Cloonamore Inishboffin | Comprehensive coastal erosion & flood risk management study for Inisboffin Island as a whole | 5,396 | 2021 |
Wicklow County Council | Avoca River Arklow | Construction of a flood protection wall | 40,000 | 2012 |
Limerick City & County Council | Clonoughter Glin | Removal of existing pipeline, installation of 90 linear metres of new *600mm pipework, gullies & chambers & associated works | 22,500 | 2018 |
Donegal County Council | Murvagh Upper Glebe Drumchory Glebe Mullanacross and Ballybulgan | To undertake a review of the existing flood data to identify measures that could be implemented, to mitigate against future flooding of this area | 764 | 2019 |
Donegal County Council | Currindale Termon | To construct rock armour 150m long by 1m high between river and road & associated works. | 31,500 | 2019 |
Cork County Council | Riverstick & Environs | Channel Capacity Improvements & Localised Permanent Flood Defences: Clear trees/scrub/gravel along river for 5 miles/ Clean and deepen river/ Construct embankments to protect water treatment plant | 90,000 | 2010 |
Louth County Council | Salterstown Annagasson | Rock armour protection to 60-100m of unstable cliff face, rock armour to be approx. 2m high | 24,750 | 2020 |
Monaghan County Council | Bunnoe River Catchment | Study | 40,500 | 2016 |
Carlow County Council | Tinnahinch | Provision of flood barriers /Provision of small sump and portable pump / Laying of surface water pipeline and associated works. | 9,871 | 2015 |
Galway City Council | Distillery Canal / Eglinton Canal, Galway City | Create a safe access to the siphon, in order to carry out investigative works & detail the remedial works required.Carry out any emergency repair if necessary | 90,000 | 2013 |
Donegal County Council | Elmwood Downes Letterkenny | Provide storm drain & connection manholes. Connect drain to existing storm system Provide land drainage at embankment | 16,000 | 2012 |
Galway County Council | East Bridge Ballinasloe | Provide a channel downstream to the Suck.Engagement of consultant to undertake conservation impact statement / Removal / modification of sluice gates | 42,200 | 2012 |
Meath County Council | Fosterfields Athboy | Piping from affected area to local stream | 13,500 | 2012 |
Kerry County Council | Ballylongford | Coastal flooding mitigation measures | 13,777 | 2015 |
Wicklow County Council | Parkmore Baltinglass | To provide an earth embankment / bund to provide a barrier against flood waters (to be undertaken in conjunction with works in Town Centre) | 210,000 | 2011 |
Carlow County Council | Tullow | Construction\installation of walls, berms, flood gates along River Slaney / Upgrade drainage system along Thom Traynor Road / Installation of pumps and sumps | 450,000 | 2010 |
Sligo County Council | Section of coastline from Deadman's Point to Rosses Point (Lower) to include the Sand Spit to the north of Rosses Lower | Coastal erosion & flood risk management study | 57,055 | 2015 |
Clare County Council | Feakle | Installation of 50m of 450mm pipework, installation of 120m of 225mm roadside drainage & 7 no gullies. Associated works. | 31,500 | 2019 |
Cork County Council | N71 Cork Road Skibbereen | Replace the existing culvert & upgrade of existing piped system | 237,009 | 2018 |
Cork County Council | Baurnahulla_Drimoleague, P47 K772 | To mitigate flood risk by severing the hydraulic connection between the septic tank and the river if it exists. A CCTV survey to ascertain the tanks integrity. If required, the tank and pipework will be replaced. A non-return value and a permanent sump will be constructed. Ramped entrance to the driveway, banked back to earthen embankments | 22,615 | 2022 |
Limerick City & County Council | Coolfune, Fedamore | construct a 300mm storm main along the R511 to manage the surface water on both sides of the roadway | 117,225 | 2022 |
Cork County Council | Ballybrack Stream Douglas | Installation of trash screen and reinforced concrete substructure and ancillary works /Replacement of under sized culvert under Church Street | 304,200 | 2010 |
Leitrim County Council | Manorhamilton, Co. Leitrim | Leitrim County Council intends to maintain vegetation along circa. 700m section of Owenbeg River. The proposed works involve branch trimming, tree cutting and the removal of dead wood debris and fallen trees along a section of the Glenfarne river. The repair of a trailing wall and channel where the two legs of the river merge at the rear of the PreSchool and Bee Park Resource Centre, Leitrim County Council have also circa. 6 no.150mm non-return Flap Valves to install on outfalls from street drainage Gullies at this location in the same channel. | 59,558 | 2024 |
Cork County Council | Pilmore Cottages, Youghal | Coastal Erosion Risk Management Study prior to funding application for structural measures to prevent or mitigate erosion | 135,000 | 2023 |
Limerick City & County Council | Ballyshonick, Pallaskenry | Construct a 225mm storm main over a distance of 150m along the public road with D400 gullies at strategic locations to capture surface water . A proposed headwall is to be constructed at outfall to stream. | 41,310 | 2022 |
Waterford City & County Council | Ardmore Bay | The main focus of the study was erosion in Ardmore. Curragh and Ballyquin were included in the study due to their proximity to Ardmore. The study investigated the impact on Curragh and Ballyquin on erosion or flood protection measures constructed in Ardmore. This application for additional funding relates to additional cost due to the requirement of additional analysis required from the Hydraulics and Maritime Research Centre UCC. | 19,207 | 2024 |
Limerick City & County Council | Cooleen House, Bruree | Re-grading of channel & reinstatement to original cross sectional channel area, removal of existing undersized culvert with a larger culvert Associated works | 33,525 | 2021 |
Cork County Council | Carrigtohill | Carrigtohill Flood Risk Assessment Study | 72,000 | 2011 |
Offaly County Council | Brosna Village | Upgrade culverts, ancillary works | 54,000 | 2010 |
Kilkenny County Council | Callan | Kilkenny County Council are to assess the Silt Mounds at the Kcat Building, Upper Bridge Street and conduct a study in relation to the on-going issues with the current pumping arrangement that needs to be future proofed following flood events in Callan in Oct 2022. | 4,223 | 2024 |
Sligo County Council | Riverstown | Removal of trees & overgrowth to improve the flow of the Unshin River over 1km, on both banks of the river | 22,635 | 2021 |
Tipperary County Council | Coolaholiga Nenagh | Channel maintenance, replace culvert. Restore parapet walls and wing walls | 24,000 | 2010 |
Limerick City & County Council | Bosnetstown, Kilfinnane | Channel cleaning | 48,915 | 2021 |
Monaghan County Council | Shambles River Monaghan Town | Carry out an extensive ground survey of the river, clear the channel of all blockages | 10,800 | 2011 |
Wexford County Council | Seaview, Bastardstown, Co. Wexford | Works to section 3, the last 145m to protect houses to the east of the coastline, consisting of full height Rock Armour ; Section 3b. The last 45m of coastline to the east. | 295,802 | 2024 |
Wexford County Council | Bridgetown (IPP) | Provide demountable flood gates and barriers on affected properties. | 157,770 | 2022 |
Wicklow County Council | Boghall Road Bray | Stream Improvements | 180,000 | 2009 |
Leitrim County Council | Glenfarne | Clearing Of Vegetation from Glenfarne River & Protecting Properties with embankments | 81,330 | 2022 |
Donegal County Council | Glack Inch Island | Construct a new 900mm or 1050mm pipe culvert & construct an inlet headwall & a self cleaning grid | 24,300 | 2014 |
Cork County Council | Roches Point Sea Wall | Detailed Design & Construction of a Toe Wall to stabilize existing sea wall | 68,445 | 2022 |
Galway County Council | Beach Road Clifden | Rock armour works | 22,500 | 2019 |
Donegal County Council | Glen Road Carvery Burnfoot | Construct bund along existing river and tributary. Construct 450mm diameter overflow pipe Construct ramp across house access River cleaning and associated works | 16,200 | 2012 |
Tipperary County Council | Drish Thurles | Construction of a 450mm surface water pipe for a distance of 250m to an open drain along with a number of new road gullies & associated works. | 18,900 | 2019 |
Galway County Council | Kingstown Ahascragh | Clean existing open drains, redirect & pipe an existing section of open drain, remove the collapsed open drain & replace it with 900mm twin-walled culvert | 25,200 | 2015 |
Carlow County Council | Tinnahinch Loch | Installation of flood gates at key locations, place new concrete floor & up stand wall in garage | 17,280 | 2016 |
Limerick City & County Council | Foynes Yacht Club | Appointment of consultants to survey the existing defences & the appointment of contractors to carry out the works | 128,025 | 2019 |
Clare County Council | Ballycally, Shannon | Clare County Council propose to repair the breach with rock armour and gabion baskets on a layer of terram. They then propose to strengthen the embankment behind the repair with suitable imported material for a distance of 100m. The solution was designed for similar breaches on the Shannon Estuary Embankments. | 49,050 | 2022 |
Longford County Council | Farannyoogan | Replace existing road culvert with new culvert suitably sized* & raise existing road levels | 23,786 | 2021 |
Galway County Council | The Quay Kinvara (IPP) | Installation of flood gates to the doors of each of the properties as set out in the GCC report | 40,500 | 2020 |
Galway County Council | Lissard, Kilconnell, Ballinasloe | Replace & upsize existing culvert & cleaning of open drains | 18,000 | 2021 |
Leitrim County Council | Eslin River Drumod | Clear shrubbery and trees from river banks and clean three drainage channels. Provide fencing and accommodation works | 5,000 | 2011 |
Galway County Council | Skenanagh Ballinasloe | Channel maintenance works, including the removal of vegetation, upsizing of the existing road crossing & install a 900mm diameter pipe under the roadway* | 18,000 | 2018 |
Galway County Council | Aughrim, Ballinasloe | Cleaning of existing drains & upgrade piped network | 36,000 | 2021 |
Wexford County Council | Seaview, Kilmore | Rock armour cliff toe protection over approx 70 to 85m of cliff frontage immediately adjacent to access road to 14 properties at immediate risk of erosion | 367,740 | 2021 |
Wexford County Council | Wexford Harbour | Several short critical sections of the existing erosion/flood defences around Wexford Harbour to be strengthened and raised in order to avoid/mitigate future flooding | 90,000 | 2011 |
Tipperary County Council | Clonsingle Newport | Construct new flood ramp, 2 new piers & barrier foundation. Purchase of flood barrier & fixtures | 13,500 | 2016 |
Fingal County Council | Portrane Phase | Supply and installation of 517 no. concrete 'SeaBee' units as temporary interim emergency measures | 524,697 | 2020 |
Clare County Council | Ballyreen | Lay a surface water pipe to outfall | 54,000 | 2015 |
Limerick City & County Council | Camas Newcastle West | Construct storm sewer, provide and connect gullies | 14,940 | 2010 |
Kildare County Council | Newtown Kilcock | Construct overflow pipeline | 237,912 | 2010 |
Kerry County Council | Currow | Construct an upgraded reinforced flood defence embankment & associated works | 77,406 | 2017 |
Roscommon County Council | Curnalee | To install pipe & construct 4 new manholes & a sluice valve.The pipe size to be a minimum of 900mm in diameter | 1,800 | 2016 |
Galway County Council | East Bridge Ballinasloe | Provide a channel downstream to the Suck.Engagement of consultant to undertake conservation impact statement / Removal / modification of sluice gates | 15,120 | 2010 |
Offaly County Council | Moneygall | Construct new drain | 36,000 | 2010 |
Kerry County Council | Sneem | Flood Ass & hydrometric study of Sneem/Ardshellhane River | 18,000 | 2009 |
Kerry County Council | Emlaghslat Ventry | To clean silt and sand from rivers & estuary of rivers | 4,500 | 2011 |
Louth County Council | Salterstown Annagassan | Rock armour protection to 60-100m of unstable cliff face, rock armour to be approx. 2m high | 13,500 | 2019 |
Louth County Council | Seabank Castlebellingham | Rock armour protection to 20m of unstable cliff face, rock armour to be approx. 2m high | 13,500 | 2019 |
Clare County Council | Mountcashel Kilmurry | To remove and replace existing stone culvert with 900mm concrete culvert & associated works. | 18,000 | 2021 |
Donegal County Council | Lifford- N15 | Provision of 3 cattle grids or gulley systems & new 900mm diameter pipe for approx 45m Cleaning existing open drains & stream and create new open drains as required Road crossing of national primary road(length 13m) | 54,000 | 2014 |
Monaghan County Council | Dunsinare (R188) Monaghan | Installation of new culverts at entrances to nursing home, private home and forest / New culverts along commercial units & filling station | 134,472 | 2012 |
Sligo County Council | Strandhill | Capital works to provide terminal protection works to heavily used main access way to dune area and southern beach | 47,700 | 2011 |
Cavan County Council | Rantavan Mullagh | Works at the eye of the bridge | 72,000 | 2012 |
Galway County Council | Ballyconneely, Clifden | Rock armour to provide support & protection along coastline at rear of property | 54,000 | 2019 |
Roscommon County Council | Rockland | Install new culvert under R357 (600mm diameter with collection chamber and connection to existing open drain) | 14,850 | 2016 |
Tipperary County Council | River Suir Loughmore | Removal of obstructions & improvement of Water Conveyance in part of the River Channel which is not a Drainage District | 45,000 | 2015 |
Cork County Council | Killeagh | Cork County Council propose river cleaning (1,100m approx.) to include tree cutting and removal of overhanging trees and branches, vegetation removal downstream of N25 bridge, and compound channel downstream of N25 to Greenway Bridge. | 73,125 | 2024 |
Galway County Council | Crowe St Gort | Purchase of pump which will pump water from Crowe St. | 36,000 | 2010 |
Galway County Council | Cloonamore, Inishboffin | CFERM Study – Value of Enjoyment Survey | 8,461 | 2023 |
Galway County Council | Derrymullan Ballinasloe | Construction of a flood defence wall | 354,962 | 2011 |
Galway County Council | Cloonrelagh | Replace and upsize existing pipes along with construction and cleaning of open drains | 25,200 | 2020 |
Galway County Council | Ardskea More Corofin | Construct a maximum 2m high earthen flood defence embankment along the bank of the Abbert River for approximate length of 200m | 28,890 | 2017 |
Galway County Council | Clonkeenkerrill | To install drain to divert existing drains to river | 12,600 | 2022 |
Louth County Council | Baltray | To repair the sea defence, including: realignment and raising of a 21m section of the existing promenade wall re-point & fill low level voids on seaward side to prevent further water ingress structural analysis of wall. | 54,000 | 2016 |
Tipperary County Council | Ballinderry | Install new stone filter drain with perforated 225mm storm pipe & large gully | 47,700 | 2016 |
Leitrim County Council | Rossinver | Dredge river channel, construct an earthen bund and a retaining wall, cut back trees | 59,600 | 2017 |
Cork County Council | Ballymakeera, Ballyvourney | Flood defence structure, with suitable impermeable barrier. Remedial works to 90m of an existing stone wall which will then form part of the flood defences thus removing the need for sandbags at this location. | 151,847 | 2024 |
Waterford City & County Council | Clonea Power | Replace existing flood walls with new flood walls- 1.5m high & associated works | 116,238 | 2018 |
Louth County Council | Bellurgan | Proposed works will include laying of rock armour along 75m Shoreline to max height of 2m or to existing road level. | 135,000 | 2023 |
Louth County Council | Drummullagh, Omeath | Proposed works will include strengthening of existing boundary wall foundations with mass concrete slab and installation of rock armour over a length of 35m | 62,100 | 2022 |
South Dublin County Council | Owendoher River | Increase the height of the existing reinforced concrete wing/wall Continue this reinforced concrete retaining wall up the banks of the Owendoher River | 108,000 | 2012 |
Roscommon County Council | River Jiggy | Channel maintenance and upgrading of culverts in selected areas | 450,000 | 2010 |
Donegal County Council | Inver | Construct a row of rock armour along the line of the existing gabions in order to protect them from further damage | 18,000 | 2020 |
Cork County Council | Finure-Guileen Cliff | Progress project to detailed design and construction stage for cliff stabilisation works to include fill with rock armour protection at the toe and associated works. | 495,000 | 2024 |
Donegal County Council | Maghery (Maghery Bay Coastal Flooding and Erosion Risk Management Study) | Coastal Flooding and Erosion Risk Management Study | 76,500 | 2018 |
Galway County Council | Roxborough, Kilchreest | Revised study and works | 40,253 | 2022 |
Sligo County Council | Ransboro Ballybeg | Hydrogeological Study | 13,500 | 2019 |
Louth County Council | Bellurgan Embankment | Study | 33,750 | 2011 |
Cork County Council | Ballintubber | Lay 940mm of 450mm diameter pipe from the northern boundary of the nursery (Irish Plant Propagation Ltd) to the outfall to existing stream approximately 940m south | 225,361 | 2022 |
Galway County Council | Lackagh Beg | New drainage system | 13,500 | 2010 |
Monaghan County Council | Kilmore East Rockcorry | Constructing/raising of road foundation & associated works | 65,700 | 2018 |
Laois County Council | Teinweir, Co. Laois | Removal of deadwood/debris and pruning of trees that are causing restrictions on approximately 3.5km of the River Nore in South Laois from the townland of Teinweir off the N77 642422.65E, 675835.151N (where phase 3 works ended) to Laois County bounds with Kilkenny 643986.268E,673629.116N. This section of River Bounds County Laois on the East Bank and County Kilkenny on the West Bank. | 55,800 | 2024 |
Galway County Council | Cooleran Turloughmore | Dig 240m open drain (remove trees and ditch) Lay culvert & 90m of pipe to drain (900mm diameter) & associated works | 9,450 | 2018 |
Donegal County Council | Milford (Drumbern) | To divert 600m of drainage to opposite side of road, increase size of outlet pipe & construct manhole | 5,000 | 2013 |
Laois County Council | River Nore- New Bridge to Knapbridge | Cleaning of archways at New Bridge on the L1659 at Cloncough, removal of debris & tree pruning | 27,000 | 2018 |
Limerick City & County Council | Ballyellinan | Limerick City & County Council (LCCC) are to construct 225mm x 200m storm main access chambers and gullies along the L1220 to manage surface water on both sides of the row of houses. LCCC will also implement a storm main to outfall to a sV-Drain located in a field north of the row of dwellings (Permission Granted). | 70,313 | 2024 |
Galway County Council | Pribbaun Roscahill | Constuction of a flood wall & associated works | 65,376 | 2020 |
Clare County Council | Victoria Court & Gordon Drive, Ennis | Hydrological Study | 22,000 | 2022 |
Waterford City & County Council | Ardmore Sea Wall | Replacement of a 15m section of seawall, replace with a new single concrete wall and foundation structure | 99,000 | 2017 |
Kerry County Council | Waterville | Refurbishment and strengthening of a beach friendly rock revetment at the Promenade Waterville. | 35,492 | 2023 |
Galway County Council | Clonfert Co. Galway | Galway County Council propose to construct an earth bund at the rear of the properties and a retaining wall at the north-eastern and south-western borders of the houses. Both will be designed to protect against the 0.1% AEP MRFS pluvial event. Channel maintenance near the four properties is also proposed for the two drains that run parallel to the proposed retaining walls. The details of the proposed works are set out in Tobin consulting engineer’s Preliminary Design Report. Galway County Council propose to undertake maintenance works to culverts within the catchment to improve outflows of pluvial flooding from the flood plain while ensuring protection from any flooding from the River Shannon. This may include modification of upstream drainage channels and diversion of flow away from the flood plain to other areas available for flooding where available and agreed with third parties. | 119,327 | 2024 |
Galway County Council | Kilcrow River, Killimor | Hydrological, Environmental Assessment & Cross Section Survey of the river & bridge works | 36,559 | 2022 |
Tipperary County Council | Coopers lot, Cashel, Thurles, South Tipperary | Geomorphological analysis, Hydrological modelling and modelling assessment. | 22,500 | 2023 |
Waterford City & County Council | Aglish Bridge | Survey & access bridge replacement | 47,700 | 2017 |
Leitrim County Council | Dromore / Carrigeen | Lower level of existing open drain & leave open channel capable of taking flood waters. Clear away obstruction up and downstream of the small bridge & cut back trees that hang over the river | 8,116 | 2017 |
Monaghan County Council | Lisnagunnion Flood Mitigation Works | Installation of a pipeline to divert flood waters | 90,000 | 2014 |
Tipperary County Council | Galbertstown Holycross | Construct a new surface water storm drain 400m long including manholes and chambers and civils works, outfall to existing open drain. | 76,500 | 2021 |
Cork County Council | Coachford, Co. Cork | Additional survey work required that will include a topographical survey of the river/stream courses and CCTV survey of the existing culverts. | 30,420 | 2024 |
Galway County Council | Ballyglass Turloughmore | Assess area downstream for discharge and install culvert under N63 | 18,000 | 2010 |
Galway County Council | Clarin River from Attymon to Clarinbridge - Revised | Hydrological Study of Clarin River Basin area | 45,000 | 2023 |
Galway County Council | Cloonamore - Inishboffin | Comprehensive coastal erosion & flood risk management study for Inishbofin Island as a whole | 6,300 | 2022 |
Cork County Council | Durrus Pre-School ,The Pavillion (IPP) | Proposal is to provide Flood barriers at each of 8 no. doors to prevent water entering the pre-school during flood events. | 15,366 | 2023 |
Monaghan County Council | Drummillard/Lakeview Castleblayney | Remove existing 600mm diameter pipe & replace with 900mm diameter pipe. Supply & erect non-return valve & chamber on network | 37,530 | 2016 |
Cork County Council | Bayview B&B, Glandore | Stabilize the cliff face with ground anchors and to protect against erosion with a sprayed concrete covering. | 225,353 | 2022 |
Wexford County Council | Bridgemeadows, Lyre River, Enniscorthy | Repair / replacement of sluice gate & associated works | 34,392 | 2021 |
Limerick City & County Council | Corcamore Clarina | Drainage works for 0.5km | 81,000 | 2010 |
Limerick City & County Council | Shanagolden | Provide trash screen with overflow facility | 45,000 | 2015 |
Cork County Council | Kilmore, Ballinspittle, Kinsale | Replacement of culvert with Section 50 compliant culvert. Review impact of 600mm culvert through the GAA pitches. | 150,000 | 2023 |
Louth County Council | Rampark Lordship | Construction of rock armour revetment for 65m | 14,400 | 2016 |
Sligo County Council | Strandhill | Beach Revetment South side coastal study to establish possible solutions and plans for future dune and shoreline management Capital works to provide terminal protection works to heavily used main access way to dune area and southern beach | 423,000 | 2010 |
Galway County Council | Tynagh Road | Collect surface water run off from the agricultural lands opposite the property and carry it in a combination of open channel and piped sections through both the existing road margin and within adjacent agricultural lands | 31,603 | 2015 |
Dun Laoghaire / Rathdown | Deansgrange Stream | Realign stream & embankment | 122,339 | 2015 |
Fingal County Council | The Grange Malahide | Construction of bund/berm & associated works | 93,600 | 2013 |
Galway County Council | Leenaun Village | Works to walls & study for full assessment of the coastline | 58,500 | 2018 |
Galway County Council | Greenville Caltra | To collect surface water run off by means of a filter drain and a catch pit/manhole. Installation of a new 600mm piped culvert & associated works | 9,990 | 2013 |
Galway County Council | Ryehill | Install pipe for 260 metres / Install gullies, cattle grids and other water collection methods at number of locations | 32,400 | 2012 |
Galway County Council | Flaskagh Beg Dunmore | Replace stone culvert with a precast concrete box culvert of similar X-Section to the open channel to increase the capacity of the bridge | 23,400 | 2011 |
Galway County Council | Derryoober Woodford | Repairs to embankment | 13,500 | 2018 |
Kerry County Council | Flesk River Glenflesk (Phase 1 & 2) | Clearance of vegetation of the river bank between Curreal Bridge at Glenflesk Village to Gortahoosh Bridge & Loo Bridge and associated works | 53,631 | 2019 |
Galway County Council | Thornfield Portumna | Replace the existing agricultural access road culverts with 900mm twin wall piped culverts & ancillary works | 17,360 | 2015 |
Galway County Council | Rahins Mountbellow | Replacement of culverts, regarding of channels | 13,500 | 2010 |
Clare County Council | Lahinch & Miltown Malbay | Works | 45,000 | 2009 |
Tipperary County Council | Coopers lot, Cashel, Thurles, South Tipperary | Geomorphological analysis, Hydrological modelling and modelling assessment. | 45,000 | 2022 |
Carlow County Council | Mortarstown Carlow | To construct a pump station & associated works | 14,400 | 2019 |
Leitrim County Council | Lough Bran Carrick-on-Shannon | Removal of vegetation/blockages alongside the channel, improve bed level gradient & associated works | 23,122 | 2019 |
Galway County Council | Tierney’s Yard | Install 170m of 600mm diameter surface water drain, two manholes & a petrol interceptor | 27,000 | 2017 |
Galway County Council | Loughaunboy Caltra Balllinasloe | Replace existing stone culvert with culvert of larger capacity & regrade existing open drains | 11,700 | 2012 |
Louth County Council | Ballagan | The works will involve replacement of sections to the existing Sea Wall and repairs to other locations along the Sea Wall | 100,472 | 2023 |
Donegal County Council | Inch Island Causeway | Strengthen existing wall & build new wall | 54,000 | 2010 |
Tipperary County Council | Coopers lot, Cashel, Thurles, South Tipperary | Ground Investigation Surveys and SI | 107,100 | 2023 |
Waterford City & County Council | Clonea Power | Replace existing flood walls with new flood walls- 1.5m high & associated works | 26,256 | 2019 |
Tipperary County Council | Doon Araglin | Excavation of a new drainage ditch, cleaning an existing deep drainage ditch, installation of drainage pipes and electric fencing | 14,580 | 2011 |
Fingal County Council | Portrane / Rush | Coastal Erosion Risk Management Study | 57,800 | 2013 |
Roscommon County Council | Beagh Brabazon Ballinasloe | To install 250m length of 900mm twinwall HOPE drainage pipe with 4 manholes | 63,000 | 2016 |
Galway County Council | Caherduff Gort Road | Clear & reinstate open drain | 5,400 | 2010 |
Monaghan County Council | Edengilrevy | Lower river channel & upsize two field access culverts | 21,600 | 2016 |
Roscommon County Council | Moneymore | To install culvert drain & inspection chamber | 20,700 | 2016 |
Longford County Council | Tenelick Colehill | Improve / drain the land drainage over 1.5kms, install a 900mm diameter pipe at 1-2 crossings to improve flow of water | 19,800 | 2017 |
Cork County Council | Lower Adamstown Ballinhassig | Replace culvert under R613 with a Section 50 compliant culvert. | 40,000 | 2021 |
Galway County Council | Rathgorgin Athenry | Installation of pipeline / Provide outfall to local drain / Cleaning of existing drainage channel | 45,000 | 2010 |
Galway County Council | Ballyglass Turloughmore | Construct a new pipe from existing open drain to existing piped drain in N63 verge | 4,860 | 2015 |
Sligo County Council | Strandhill Bay | Coastal Erosion & Flood Risk Management Study | 5,836 | 2022 |
Galway County Council | Grattan Park Mountbellew | To replace and upsize the existing 600mm diameter pipe to 1050mm diameter pipe & associated works | 50,400 | 2018 |
Limerick City & County Council | Funcheon Bridge | Removal of flood retaining debris and overgrowth on both banks | 13,284 | 2021 |
Galway County Council | Knock Barnadearg | Channel maintenance works | 15,750 | 2015 |
Westmeath County Council | River Gaine Ballynagall Mullingar | Install new pipe & culvert | 54,000 | 2010 |
Galway County Council | Corgerry Oughter Menlough | Replacement of culverts, regarding of channels | 16,200 | 2010 |
Galway County Council | Portumna – Ennis Road (R352) at St. Josephs Road | Upgrade pipe / culvert on R352 at St. Josephs Road / Clean and widen existing drain to Lough Derg outfall | 27,000 | 2010 |
Galway County Council | Clooncallagh Moylough Ballinasloe | Construct new open drain for approximate distance of 80m, provide for 60m of 600mm diameter surface water pipeline & associated works | 14,940 | 2017 |
Limerick City & County Council | Corbally | Rebuild the embankment with rock gabions & compacted clay | 41,400 | 2016 |
Roscommon County Council | Ballintober Village | Replace existing culvert with larger capacity structure | 90,000 | 2010 |
Galway County Council | New Inn Village | Regrade stream & upgrade culvert | 31,500 | 2010 |
Roscommon County Council | Killukin River Carrowreagh | Study Only | 5,036 | 2010 |
Mayo County Council | Bellavary | Works – Renforce earth banks, install piping | 37,845 | 2009 |
Galway County Council | Ryehill Demesne Monivea | Replace existing culvert with larger capacity structure | 14,400 | 2010 |
Galway County Council | Kiltartan & Coole Gort | Reinstatement of culverts at Kiltartan, new culverts, improvements & cleaning of existing masonry arch bridge and associated works | 351,000 | 2011 |
Roscommon County Council | Four Roads Area | Study of catchement to identify relief works | 18,000 | 2010 |
Tipperary County Council | Clareen Cross Moyaliff Ballycahill | To construct approx. 600m of 300mm diameter pipe line and associated accommodation works | 33,408 | 2011 |
Mayo County Council | Dookinelly Acill Island | Provide an outlet open drain to the sea & provide roadside drainage | 45,000 | 2010 |
Longford County Council | Killeen Granard | Replace culvert with 1.35mm diameter pipe | 18,800 | 2016 |
Fingal County Council | Portrane Phase 1 | Supply and installation of 400 no. concrete 'SeaBee' units as temporary interim emergency measures | 422,008 | 2020 |
Galway County Council | Whyte's, Carrownamadra Kinvarra | Construct a 140m length of stone faced concrete block retaining wall, 750mm high around a section of the property & to install a sump & road crossing. | 13,500 | 2016 |
Galway County Council | Rahins Mountbellew | To clean existing open roadside drains for approximately 200m, construct headwall at end of proposed 600mm diameter pipeline & associated works | 36,000 | 2018 |
Mayo County Council | Neale-Cross | A prefeasibility study, stage 1 feasibility study, preferred option identification & surveys | 151,635 | 2018 |
Monaghan County Council | Seaveagh Glaslough | Erection of earth embankment Provision of two pumping stations | 30,000 | 2011 |
Donegal County Council | Downings Beach | Rock armour protection to base of damaged embankment- restore embankment with granular material | 45,000 | 2013 |
Leitrim County Council | Tully Lough Fenagh | Study | 10,000 | 2013 |
Offaly County Council | Newtown to Ballybritt | Install 1m pipes & associated works | 18,888 | 2019 |
Monaghan County Council | Moy Etra Castleshane | Construct embankment around dwelling house & provide a pump to pump out surface water | 15,000 | 2012 |
Longford County Council | Ratharney Abbeyshrule | Improve / drain the land drainage over 1km, install a 900mm diameter pipe at main road crossing & next to dwelling to improve flow of water | 18,000 | 2017 |
Tipperary County Council | Ballinderry, Nenagh | Install new stone filter drain with perforated 225mm storm pipe and long gully & discharge via 300mm storm pipe. Total length 455m | 72,292 | 2018 |
Limerick City & County Council | Marine Cove Road Foynes | Provide a new concrete box culvert from the headwall at Marine Cove Road to the outfall into the Shannon Estuary | 234,000 | 2019 |
Galway County Council | Roo, Tierneevin, Gort, Co. Galway | Galway County Council intend to upgrade the embankment. Install a toe drain (French drain). Install a sump & pump. Divert road run-off. Install a non-return valve on the foul water line. | 18,000 | 2024 |
Galway County Council | Ballyglass Turloughmore | To construct an open drain from the existing ditch/open drain for a distance of circa 275m into an existing culvert under the M63 | 1,125 | 2015 |
Clare County Council | Querrin Beach | Reconstruction of culvert and sluice | 39,750 | 2023 |
Galway County Council | Cahernaglass, Monivea, | Install 300m of 450mm diameter drainage pipe into nearby drain, Clean existing drain and install earth embankment at rear of properties | 24,750 | 2023 |
Kerry County Council | Incherea | The strengthening and raising of an existing embankment | 80,000 | 2012 |
Roscommon County Council | Four Roads | Installation of V-ditch open drain with mini cross sectional area of 0.94sq.m over a distance of 963m plus a 900mm diameter concrete sewer to discharge to Cloonlaughnan Lake pipe for a distance of 783m | 202,677 | 2014 |
Kilkenny County Council | Ballyfoyle Road | Construction of new culvert across Ballyfoyle Road / Construction of new culvert in private garden by trenchless technology / Clean open channel and other culverted sections of the stream | 72,000 | 2012 |
Carlow County Council | Cassidy's House Gotham | Construct reinforced concrete flood wall & provide demountable flood gates | 6,030 | 2016 |
Louth County Council | Dundalk Bay (Greenore, Dillonstown & Blackrock) | Coastal Erosion Risk Management Study | 81,000 | 2015 |
Donegal County Council | Downings | Replacement of existing box culvert with larger box culvert. Reinstatement of parapet walls. Improvements to river channel | 63,000 | 2011 |
Galway County Council | Rinrush Gort | Installation of a 3m wide roadway through an area of land that floods during events, to allow for emergency access & will also permit additional access | 70,830 | 2019 |
Leitrim County Council | Ballinaglera Village | Clearance of drainage channel from properties to the lake- 1.3km. Provision of beams at rear of properties- 110m | 99,930 | 2021 |
Wicklow County Council | R762 Delgany | Lay 230m of 12” UPVC SW Line / Reinstatement of road / Construction of manholes /Install gullies / Connect existing gulliesInstall new pipe line | 40,230 | 2009 |
Carlow County Council | Leighlinbridge | Flood alleviation works along banks of River Barrow at Carlow Road (Lord Bagenal Hotel) & Barrow Track (Garrison House), together with ancillary drainage works | 9,871 | 2015 |
South Dublin County Council | River Poddle | Redesign and installation of three trash screens Works to two restrictive pedestrian bridges Maintenance of riverbank / dredging and widening of River | 250,000 | 2012 |
Leitrim County Council | Belhavel Killargue | Clear away obstruction up and down stream of the bridge on the R280. Cut back trees that hang over the river | 10,170 | 2014 |
Galway County Council | Baile an tSagairt An Spiddéal | Drainage maintenance works on approximately 700m of channel to include the removal of flood debris and blockages under the bridges and the controlled treatment of the invasive species along the route of the works | 13,596 | 2015 |
Wicklow County Council | Boghall Road, Bray | Upgrade pipe & channel | 180,000 | 2010 |
Limerick City & County Council | Shanpallas Pallaskenry | The drainage maintenance of approx.700m of existing land boundary drains and the removal of high point of rock outcrop | 22,500 | 2020 |
Galway County Council | Lowville Ahascragh | Construct three head walls & a new open drain, replace existing pipes, reinstate public roadway & private driveway & associated works | 63,000 | 2017 |
Galway County Council | Roo Kinvara | Culvert upgrade, channel improvements & environmental reports. | 76,500 | 2016 |
Galway County Council | Inis ni Pier Roundstone Conemara | Construct coastal protection to the public access road | 210,600 | 2010 |
Roscommon County Council | River Jiggy | Channel maintenance and upgrading of culverts in selected areas | 7,200 | 2013 |
Galway County Council | Derrydonnell Oranmore | Channel maintenance, pipes, replacement of culverts | 17,224 | 2014 |
Limerick City & County Council | Finoo Ballyhahill | Removal of existing pipeline, installation of 90 linear metres of new *600mm pipework, gullies & chambers & associated works | 27,000 | 2018 |
Wexford County Council | Badgers Hill | Remove the access to the property and continue the bund/ditch already around the property passed the lowest point. Create a new entrance on the higher section of the road to prevent risk of flooding. | 25,869 | 2024 |
Sligo County Council | Mardyke Road Cartron | Construct 200m of 1.0m high x 0.225m wide skirting wall along most critical stretch of 500m long structure | 46,800 | 2020 |
Galway County Council | Knockaunglass Athenry | Carry out channel maintenance and re-grading works where necessary downstream of the existing culvert for approx 1000m along with increasing the capacity of the culvert via de-silting/cleaning works | 11,237 | 2015 |
Wicklow County Council | L52001 Redford Park Greystones | Construction of a 1m high block concrete wall with foundations | 6,300 | 2009 |
Limerick City & County Council | Askeaton | The appointment of consultants to prepare a detailed design of proposed improvements to include costings and cost benefit analysis | 30,000 | 2015 |
Fingal County Council | Aspen Swords | Increase the channel capacity by widening the Gaybrook stream along a 200m length at Aspen | 54,000 | 2011 |
Galway County Council | Cloonreleagh West Mountbellew | Replace existing culvert with culvert of larger capacity & regrade existing open drains | 9,000 | 2011 |
Limerick City & County Council | Lisbane, Shanagolden, L1220 | The proposed works are located to the south east of Shanagolden village. Limerick City & County Council (LCCC) are to construct a 300mm storm main along the L1220 to manage surface water on both sides of the row of houses. There will be a soakaway system for the drain pipe which will be located to the rear of one of the properties. | 128,889 | 2024 |
Galway County Council | Blackrock Peterswell Gort | Construct an earthen embankment- crest level is required to have a minimum of 500mm freeboard above the highest recorded flood level which occurred in 2015. A drainage system to cater for internal surface drainage will also be required. Relevant environmental criteria shall be complied with as the proposed works are adjacent to the Peterswell Turlough SAC | 18,000 | 2016 |
Laois County Council | Water Castle bridge to Tinwear | Removal of deadwood/debris and pruning of trees that are Causing restrictions on approximately 6.5km of the River Nore in South Laois from Watercastle Bridge in the townsland of Abbeyleix Demesne | 63,000 | 2023 |
Limerick City & County Council | Groody River Ballysimon | Installation of a fully welded and tested smooth HDPE liner to outer bank slope | 11,700 | 2013 |
Tipperary County Council | Tivoli Heights Clonmel | Works-Installation of new grill to improve flow, constructionof wing walls to side of culvert/pipe | 1,373 | 2010 |
Donegal County Council | Main St. Rathmullen | To put a new road crossing 50m to the south at a higher level, and associated works | 31,500 | 2011 |
Galway County Council | The Quay, Kinvara | Installation of flood gates to the doors of each of the properties as set out in the Galway County Council report | 1,962 | 2021 |
Longford County Council | Mosstown Kenagh | Improve / drain the land drainage, install a 1050mm diameter pipe at main road crossings to improve flow of water | 55,800 | 2017 |
Waterford City & County Council | Ardmore Bay | Ardmore Bay - Coastal Erosion and Flood Risk Management Study. | 61,815 | 2021 |
Laois County Council | River Nore - Phase 2 | Removal of deadwood/debris and pruning of trees that are causing restrictions on approximately 6km of the River Nore in South Laois | 63,000 | 2022 |
Longford County Council | Moygh Ballymahon | Upgrade culvert | 163,857 | 2010 |
Roscommon County Council | Miltown Castleplunkett | Study | 2,250 | 2010 |
Galway County Council | Caltragh, Laurencetown | Channel maintenance works | 10,800 | 2014 |
Galway County Council | Castlenancy Gortymadden | Carry out channel maintenance works upstream and downstream of the existing culverts & increasing the capacity by upgrading with a 900mm diameter pipe | 65,250 | 2018 |
Galway County Council | Eskemurray Ballinasloe | Raise & strengthen a 60m section of existing stone boundary wall, installation of flood gates, drain & sump | 26,100 | 2017 |
Tipperary County Council | Railstown Cashel | Widen Moyle Stream, repair bridges & culverts | 45,360 | 2010 |
Roscommon County Council | Feorish River Ballyfarnon | Flood mitigation works on the Feorish River | 31,500 | 2020 |
Galway County Council | Caheroyn Avenue Athenry | Construct reinforced concrete wall, construct sump, remove existing fencing & walls along river & associated works | 6,300 | 2018 |
Roscommon County Council | Roxboro | Construct road crossing with 600mm diameter pipe to outfall drain for 120m through farm property | 8,745 | 2011 |
Clare County Council | Doolin | Coastal erosion & flood risk management study | 55,000 | 2015 |
Louth County Council | Seabank Castlebellingham | Rock armour protection to 20m of unstable cliff face, rock armour to be approx. 2m high | 16,200 | 2019 |
Leitrim County Council | Cornamucklagh South, Ballinaglera | Clearance of drainage channel from properties to the lake – 900m. Reinstatement of berms along river & reinstatement of private lane | 22,299 | 2021 |
Cork County Council | The Glen Glenbrook Passage West | Study & remedial works | 99,000 | 2010 |
Leitrim County Council | Stoney River, Ballinaglera | Clearance of drainage channel from properties to the lake - 1.3km Extension to existing berm at back of property - 65m Underpinning private pedestrian bridge | 30,203 | 2021 |
Waterford City & County Council | Kilfarrassy to Tramore | Study of Coastal area from Kilfarrassy to Tramore Beach | 81,724 | 2022 |
Clare County Council | R352 Spancilhill Ennis | Construction of 520m of 900mm flood relief culvert with associated inlet and outlet chambers | 52,000 | 2012 |
Leitrim County Council | Dromore/Caddagh Dromahair | Clear river and remove obstructions, cut back over hanging trees, create bund along road edge of L4268 | 9,017 | 2013 |
Dun Laoghaire / Rathdown | Stradbrook Stream Monkstown | Replace culverts at two locations Screen replacement | 153,000 | 2012 |
Kildare County Council | Tori River Celbridge | Works-Diversion of river, upgrade of channels, construction of new channel, general maintenance | 150,000 | 2009 |
Wexford County Council | Bridgetown | Complete a feasibility study on the impact of flood, mitigation and prevention options, including modelling of the options. | 70,200 | 2022 |
Mayo County Council | Bohola Village | Replacement of existing steam culvert, installation of a field drainage culvert, maintenance / river cleaning & associated works | 58,666 | 2020 |
Louth County Council | Bellurgan | To facilitate the transport of and stockpiling of currently available embankment fill material for planned works in 2016 | 45,000 | 2015 |
Tipperary County Council | Capparoe, Nenagh | Supply & lay 80m of 300mm/120mm/300 diameter/120mm 450mm diameter pipeline Associated works | 43,042 | 2020 |
Galway County Council | Cahermore Kinvarra | Construction of a concrete box culvert & associated road raising | 22,950 | 2014 |
Tipperary County Council | Nenagh Road Borrisoleigh | Construction of 120m of a 450mm surface water pipe along with 3 new gullies & associated works | 27,000 | 2019 |
Limerick City & County Council | Kilroath R511 Meanus | LCCC propose to construct a 300mm storm main along the R511 to manage surface water on both sides of the road width. Storm main to outfall to the existing stream .Includes for chambers, gullies and surface reinstatement | 101,952 | 2024 |
Kerry County Council | Kenmare Town | Flood Ass & hydrometric study of the River Finnihy. Removal of beam / drain under Finnihy Bridge / Installation of gauges / Establish monitoring programme.(not proceeding with the removal of beam/drain) | 13,500 | 2009 |
Kerry County Council | The Spa Seawall North Kerry Way | Repair to a breach in the sea wall along the North Kerry Way National Trail | 24,170 | 2020 |
Clare County Council | Aughinish Island New Quay | Repair breaches in embankment, strengthen & reinforce embankment with rock armour. Repair walls. | 81,000 | 2019 |
Cork County Council | N71 Cork Road Skibbereen | The replacement of a culvert & upgrade piping systems. | 41,211 | 2022 |
Carlow County Council | Leighlinbridge | Flood alleviation works along banks of River Barrow at Carlow Road (Lord Bagenal Hotel) & Barrow Track (Garrison House), together with ancillary drainage works | 33,295 | 2013 |
Kerry County Council | Cullavaw River Rathmore | The removal of bushes, shrubbery & overhanging branches along the channel for 5.5 kms. Some removal of deposition from the channels | 40,000 | 2013 |
Dun Laoghaire / Rathdown | Packenham Rd Monkstown | Install new screen and overland route | 43,200 | 2011 |
Offaly County Council | Bog Road Portarlington | To upgrade roadside drains, replace 3 no culverts at land access points & associated works | 132,795 | 2019 |
Cork County Council | Ballinveltig Curragheen Bridge | Replace the existing double culvert with one large culvert of equal width & height Construct an overflow culvert downstream & a land drain | 180,000 | 2017 |
Galway County Council | Kilcloghans Tuam | To construct a reinforced concrete flood defence wall, a 600mm pipe and flap valve to be fitted to the outfall of the existing open land drain to the Clare River | 19,845 | 2016 |
Galway County Council | Maghanearla Portumna | Lay 100m of 450mm twin wall pipe in the existing grassed margin and tie-in with the existing manhole upstream of the culverted road crossing | 5,619 | 2015 |
Galway County Council | Liscune Upper Ballymacward Ballinasloe | Replace existing culvert with culvert of larger capacity, clean & regrade open drain, clean swallow hole & install stock proof fence | 16,200 | 2011 |
Cork County Council | Kilumney Village | Study | 27,000 | 2018 |
Clare County Council | Cloonbony | Upgrade Culvert | 36,000 | 2010 |
Galway County Council | Labane Gort | Maintenance & improvements to existing swallow holes | 9,000 | 2016 |
Laois County Council | Clonnygowan | Construct embankment around properties to prevent flood waters entering properties. Remove exiting low level foot bridge to be replace with precast concrete unit. | 88,200 | 2023 |
Galway County Council | Deerpark Ballinasloe | Carry out drainage works upstream of the main Deerpark River channel | 19,000 | 2016 |
Carlow County Council | Tullow | Construction\installation of walls, berms, flood gates along River Slaney / Upgrade drainage system along Thom Traynor Road / Installation of pumps and sumps | 80,311 | 2013 |
Galway County Council | Leam Oughterard | To replace 2 no 600mm culverts with 2 no 1.2m culverts | 18,000 | 2019 |
Wexford County Council | Clone Road Phase 2 | Works | 112,500 | 2010 |
Cork County Council | Crookstown | Permanent flood walls & embankments | 318,600 | 2010 |
Galway County Council | Ardacong Tuam | Construct a surface water pipe along the route of the Tuam bypass for a distance of 750m to a tributary of the River Clare | 83,700 | 2016 |
Louth County Council | Ballagan Greenore | To repair the sea armour | 18,000 | 2013 |
Kerry County Council | Feoghanagh | Clean silt and sand from rivers and estuaries | 5,400 | 2009 |
Roscommon County Council | Ballyglass Lower Ballinaheglish | Increase cross sectional area of channel 1600m length and replace culverts as necessary | 28,800 | 2012 |
Dublin City Council | Dodder Estuary,Fitzwilliam Quay | Restore section of Quay Wall on Fitzwilliam Quay | 250,000 | 2011 |
Roscommon County Council | Lough Funshinagh and Environs – Ballagh, Lisfelm, Srahauns, Lysterfield | Study | 72,000 | 2018 |
Mayo County Council | Kilmurray National School Crossmolina | Replace existing riverside wall with reinforced concrete wall to specified height, and provide pump sump | 20,000 | 2020 |
Cork County Council | Roches Point Sea Wall | Detailed Design & Construction of a Toe Wall to stabilize existing sea wall | 9,654 | 2023 |
Galway County Council | Cross St/Lake Road, Loughrea | Installation of additional gullies / removal of existing culvert & replacement with a culvert of greater capacity | 5,000 | 2012 |
Cork County Council | Midleton Northern Relief Road | Study | 19,000 | 2013 |
Monaghan County Council | Clones to Finn River | New bridges / channel maintenance | 31,500 | 2010 |
Monaghan County Council | Kilmore East | Clean stream from Kilmore East to Milltown Bridge. | 12,690 | 2009 |
Tipperary County Council | Mullinahone | Removal of debris from the channel and banks prior to building a foundation and retaining wall along the banks A design & method statement to be developed | 119,700 | 2020 |
Kerry County Council | Glenflesk | Study of recurring flooding in Glenflesk Village and N22 | 13,500 | 2009 |
Donegal County Council | Liscooley | Study to assess capacity issues within watercourse & interaction with infrastructure | 2,866 | 2020 |
Clare County Council | Gullets Cross, Carrowmore, Cratloe | Divert the flow from the spring into a nearby stream, approx 500m away. Installation of road gulllies to remove any surface water buildup | 76,500 | 2023 |
Galway County Council | Dark Road Castletaylor North Ardrahan | Study | 9,000 | 2016 |
Galway County Council | Pollnagarragh East Mannin Cross Craughwell | Maintenance & cleaning of existing drainage system | 6,750 | 2014 |
Galway County Council | Termon North Gort | Phase 1 of the Environmental Assessment | 15,715 | 2012 |
Galway County Council | Coolarne Turloughmore | Replace existing 450mm pipe with 560m of concrete 900mm piping and associated works | 51,750 | 2011 |
Tipperary County Council | R-691- 4 Ballinure School | Clear out 500m of open drain on agricultural land & dispose of material | 13,500 | 2016 |
Donegal County Council | Liscooley | Study to assess capacity issues within watercourse & interaction with infrastructure | 7,650 | 2019 |
Galway County Council | Clonbur Sports Ground Clonbur | Maintenance of riverbanks & vegetation removal, cleaning of swallow holes & construction of a 150m embankment | 36,000 | 2017 |
Donegal County Council | Magheraroarty (Ballyness Bay Coastal Flooding and Erosion Risk Management Study) | Coastal Flooding and Erosion Risk Management Study | 76,500 | 2018 |
Roscommon County Council | Valeview Castlerea | Increase capacity of existing pipe and undertake associated works | 54,000 | 2010 |
Cork County Council | Ballymakeera | Sand bag flood defence structure | 187,248 | 2018 |
Wicklow County Council | Clogga Beach at Arklow County Wicklow | Wicklow County Council’s study objectives, are to undertake a detailed coastal erosion risk management investigation and condition survey to develop an appropriate plan to best manage the risks identified to human health and life (social), the environment, cultural heritage and economic activity and to further assess and investigate the feasibility of the management plan option(s) and measure(s) being recommended. The study will follow the Study Scope and Terms of reference of Schedule A within the OPW Guidelines. | 121,500 | 2024 |
Galway City Council | Dock Road Seapoint Promenade | To seek a suitably qualified specialist consultant to provide a closer study of the outline proposals and develop both feasibility and real cost estimates around the proposed project. | 27,000 | 2024 |
Carlow County Council | Paupish Lane Carlow | Construction of chambers, installation of gates and non-return valves. Associated works | 49,500 | 2016 |
Carlow County Council | Tinnahinch Quay | Raise level by 350mm for a distance of 80m downstream of Graignamanagh Bridge, provide demountable flood gate to isolate area from flooding from Mill Race, provide demountable flood gates to each of the properties and provide 350mm up stand to existing wall along Mill Race for 20m | 31,050 | 2016 |
Wicklow County Council | North Beach – Arklow | Coastal Protection Works | 70,000 | 2010 |
Donegal County Council | Inishfree Bay | Coastal Flooding and Erosion Risk Management Study | 76,500 | 2016 |
Galway County Council | Moneen, Tuam | Install new 450mm diameter concrete pipe crossing road with headwalls/ NRV. | 54,000 | 2023 |
Galway City Council | Sruffaunacashlaun Stream & Distillery Canal | Channel maintenance on the open channel section of the stream & trash screen replacements, carry out desilting works on Distillery Channel. Tree cutting & vegetation clearing works. Prepare AA screenings, assessments & reports | 444,600 | 2018 |
Mayo County Council | Frenchbrook Kilmaine | Road re-instatement with 100mm diameter pipe, drainage piping & accommodation works | 14,850 | 2014 |
Tipperary County Council | Ardfinnan Clonmel | The provision of a pumping installation in the 'Back River' to discharge to River Suir over flood defences during flood times | 15,750 | 2011 |
Galway County Council | Moanmore East Loughrea | Upgrade existing drain / watercourse and upgrade piped culvert section of channel | 54,000 | 2012 |
Louth County Council | Salterstown Annagassan | Rock armour protection to 60-100m of unstable cliff face, rock armour to be approx. 2m high | 76,500 | 2019 |
Galway County Council | Cloonrelagh Mountbellew | Regrading of the stream & the inlet and outlet of the culvert | 11,250 | 2010 |
Donegal County Council | Circular Road Letterkenny | Installation of 98m of 750 diameter pipes | 51,773 | 2018 |
Galway County Council | Toor-Ballylee Gort | To carry out extensive channel maintenance & associated works | 50,000 | 2013 |
Limerick City & County Council | Ballykenny (Strand) | Clean open channels & provide gullies | 29,700 | 2010 |
Roscommon County Council | Correenbeg Oldtown | Remove existing 2 x 900mm diameter pipe culverts & replace with 1 no. 1500 x 1800 box culvert, remove existing 2 x 900mm pipe culverts at “Cish” & replace with 2 x 1200mm diameter pipe culverts | 36,000 | 2017 |
Sligo County Council | Carraroe (Revised) | Studies through the installation of hydro metric probes, data loggers and ancillary works in the form of a road crossing to facilitate pumping in the event of flooding | 24,292 | 2018 |
Galway County Council | Curragh Kilconnell Ballinsloe | To install a 220mm of 450mm diameter pipe with two headwalls & manholes. | 54,000 | 2020 |
Galway County Council | Newtown Abbeyknockmoy | Improvements to piped drainage system | 250,000 | 2010 |
Galway County Council | Ballyglass Kilconnell | Replace two existing culverts with culverts of larger capacity & regrade existing open drains | 19,800 | 2011 |
Tipperary County Council | Gortnahoe | Construct a new surface water storm drain 200 metres long including manholes and chambers and civils works, outfall to existing open channel. | 22,500 | 2023 |
Limerick City & County Council | Derraulin Bruree | Proposed channel improvements (widening/ deepening) to restore/maximise the channel conveyance capacity. | 36,000 | 2024 |
Kilkenny County Council | Rathcurby Kilmacow | Installation of a new 350m open drain | 33,750 | 2023 |
Clare County Council | Ballymacrogan | Provide road gullies channel & surface network | 31,500 | 2015 |
Galway County Council | Graiguenavaddoge Caltra | To construct two headwalls, clean/construct field drains, install a new 600mm diameter culvert & associated works | 14,940 | 2017 |
Limerick City & County Council | Feenagh | Construct storm sewer, provide and connect gullies | 108,000 | 2010 |
Galway County Council | Lenamore Colemanstown Ballinasloe | Replace existing stone & concrete piped culvert with culvert of larger capacity & regrade existing open drains | 16,200 | 2012 |
Meath County Council | Swan River | Construct flood embankments | 270,000 | 2009 |
Waterford City & County Council | Killadangan | Survey & works to clear restrictions at eye of bridge. Repairs to river bank | 13,050 | 2017 |
Galway County Council | Clarin River Ballydavid / Athenry | Channel maintenance, replace culvert, remove weir | 40,000 | 2010 |
Wexford County Council | Irish National Heritage Park, Co. Wexford | Seal the gully in the south-eastern corner of the carpark with a sealed manhole cover. Relocate the other two gullies circa 2-3m for the current locations install interconnecting pipe work from the new gully pots. Fit a non-return valve on the pipes in independent chambers and using the existing pipe connections to the culvert. Install a duckbill tide flex valve Break out footpath and cut back drainpipe in the north-eastern corner and back fill with concrete. Raise the level of the splitter chamber above the level of the adjacent footpath. | 27,000 | 2024 |
Cork County Council | Ballingeary & Inchigeelagh | River cleaning & maintenance works | 40,000 | 2011 |
Longford County Council | Creenagh | Improve / drain the land drainage over 1km, clean out 1200mm diameter pipe at main road crossing & install a 900mm diameter pipe next to dwelling to improve flow of water | 40,500 | 2017 |
Galway County Council | Bovinion Mountbellew | Replace existing culvert with culvert of larger capacity & regrade existing open drains | 11,700 | 2011 |
Galway County Council | Bellayarha North | Replace existing culvert with larger capacity structure | 9,000 | 2010 |
Cork County Council | Cape Clear Island South Harbour | 162,900 | 2024 | |
Wexford County Council | Arthurstown | Coastal flood defence works, comprising raised sea walls, demountable barriers & foul and surface water pumpimg stations | 414,000 | 2016 |
Galway County Council | Clarin River Ballydavid / Athenry | Channel maintenance, replace culvert, remove weir | 90,000 | 2010 |
Sligo County Council | Ballyfree | Study | 13,760 | 2018 |
Cork City Council | Cork City Walls | Repairs and upgrading of quay walls at 6 locations, Sunday's Well Rd, Grenville Place, Bachelor's Quay, Popes Quay, Sullivan's Quay and Father Mathew Quay. | 900,000 | 2010 |
Donegal County Council | Ard na gCeapairi, R257 | Replacement of existing 600mm pipe and stone culvert with box culvert and two manholes, together with road crossing and accommodation works on two dwellings | 29,700 | 2010 |
Waterford City & County Council | Passage East | Study | 15,000 | 2012 |
Monaghan County Council | Bunnoe Catchment Area | Improvement of channel conveyance, sediment control & access improvements | 279,900 | 2018 |
Cavan County Council | Crosskeys Bridge | Replace Bridge | 72,000 | 2010 |
Galway County Council | Moylough Village | General maintenance of 1800m of open channel | 170,000 | 2010 |
Galway County Council | Corrabaun New Inn Ballinasloe | Clean existing field drains & roadside drains, install a 900mm pipe for approximately 30m & associated works | 18,000 | 2017 |
Cork County Council | River Ilen Skibbereen | Replace the 36m of culvert in private lands | 72,000 | 2015 |
Leitrim County Council | Greyfield | Channel Cleaning General channel maintenance and provision of fencing | 25,000 | 2012 |
Cork County Council | Riverstick | Replacement of Ballady Culvert | 81,000 | 2012 |
Limerick City & County Council | Mona Lodge Portcrusha | Carry out works to road and pavement, construct an embankment & associated works | 42,407 | 2017 |
Limerick City & County Council | Coole Lane Newcastle West | Provide additional gullies, kerbing, aquadrain & connect to storm system. Reshape Road & Footpath | 8,000 | 2011 |
Clare County Council | Shannon Banks Parteen | Construction of an overflow, attenuation and submersible pump operation | 135,000 | 2012 |
Leitrim County Council | Glenfarne | General channel maintenance & provision of fencing Removal of blockages in river / Clearance of tributary of trees and debris downstream of Road Bridge (add to 2010/11 allocations) | 15,000 | 2010 |
Carlow County Council | Ballymurphy Tullow | Berms, retaining walls and drainage works | 31,500 | 2010 |
Cork County Council | Ballinacurra | Installation of debris screen | 5,880 | 2010 |
Tipperary County Council | Greenhills/Kilmastulla Ballina | Upgrade of the existing road surface water drainage system & associated works | 56,700 | 2018 |
Galway County Council | Rathglass New Inn | Upgrade culvert | 13,500 | 2010 |
Waterford City & County Council | Abbeyside Tournore Retention Pond Dungarvan | Lowering of existing detention pond to increase attenuation capacity. | 675,000 | 2023 |
Galway County Council | Clonfert Ballinasloe | Construct a new 450mm storm water sewer | 29,925 | 2015 |
Cork County Council | Inchigeelagh | Selectively clear bankside trees & scrub Selectively clear islands where impeding flows to mean low water level | 45,000 | 2012 |
Carlow County Council | Tullow | Construction\installation of walls, berms, flood gates along River Slaney / Upgrade drainage system along Thom Traynor Road / Installation of pumps and sumps | 9,870 | 2015 |
Mayo County Council | Ballisnahyny/Glasvally | Installation of 450mm & 600mm diameter pipe Deepening of channel including re-instatement & accommodation works | 30,600 | 2014 |
Meath County Council | Eastham Stream | Remove and relocate existing pipes and ancillary works | 22,500 | 2011 |
Tipperary County Council | Convent Road Cahir | Cleaning & deepening of existing drain / Excavation of trench / Laying of pipe bedding and 40m of concrete pipe / Construct manhole and backfill/compact / Restoration works | 31,500 | 2010 |
Galway City Council | River Corrib Galway City | Temporary flood defence measures- fenders, gates etc. | 117,342 | 2014 |
Limerick City & County Council | Con Colbert St Athea Village | Construct storm sewer, provide and connect gullies | 14,940 | 2010 |
Cork County Council | Pilmore Sluice Youghal | Repair / replacement of sluice gate & associated works | 34,392 | 2021 |
Meath County Council | Ashbourne | Design Study | 58,983 | 2015 |
Louth County Council | Blackwater River Dundalk | 1480m of river cleaning, install a new river grill | 71,820 | 2011 |
Limerick City & County Council | Glin Rd, Athea | Construct culvert & provide gullies | 27,000 | 2010 |
Mayo County Council | Doolough | Works to sea wall | 45,500 | 2009 |
Galway County Council | Caherlistrane | Install 900mm culvert & Raise road level by 500mm | 27,000 | 2010 |
Cork County Council | Clonakility | Channel capacity improvements | 350,000 | 2010 |
Galway County Council | Kylemore River Laurencetown Ballinasloe | River cleaning for 1km | 13,100 | 2012 |
Tipperary County Council | Rathkennan | Overflow pipe from lane way adjacent to houses to mitigate against flooding | 4,500 | 2015 |
Limerick City & County Council | Ruppulagh Glenroe | Clean out & reinstate existing french drain, excavate & install sump, excavate new open field drain and surface restoration of flood damaged carriageway | 13,977 | 2019 |
Tipperary County Council | Dualla Road and Waller’s Lot Cashel Town (Revised) | Study | 4,389 | 2018 |
Louth County Council | Dunleer | Detailed Flood Study | 58,500 | 2015 |
Clare County Council | Ranaghan Ruan | Flood mitigation works | 36,000 | 2010 |
Mayo County Council | Dowagh Ballinrobe | Pipeline from flood area to stream or sink hole including reinstating and accommodating works for landowners | 60,000 | 2011 |
Waterford City & County Council | Woodstown | To replace and reinforce existing coralle & replace existing flap valve | 13,500 | 2014 |
Longford County Council | Camlin River – Ballyminnion Stream | Channel reprofiling & gradient correction works | 144,000 | 2011 |
Galway County Council | Mira | Detailed study of lands – Up to 600m of 600-900mm pipe required | 67,500 | 2010 |
Galway County Council | Kilcrow River Killimor | Hydrological & Environmental Assessment of river & bridge works. | 22,500 | 2021 |
Sligo County Council | Rosses Point | Study | 40,500 | 2009 |
Tipperary County Council | The Millrace Cahir | Clean & dredge the Milrace from the River Suir to the downstream weir, remove silt & vegetation | 35,550 | 2017 |
Galway County Council | Caherawoneen South Kinvarra | Construction of box culvert bridge on existing watercourse / Road realignment | 49,500 | 2012 |
Kerry County Council | Cappaclough Camp | To clean silt and sand from drainage channels and river | 5,400 | 2011 |
Galway County Council | Eskerboy Killimor | Install a new piped drainage system to replace the existing stone & oversized culvert | 56,880 | 2020 |
Tipperary County Council | Dualla Road and Waller’s Lot Cashel Town | Study | 22,611 | 2017 |
Mayo County Council | Creggaunbaun Louisburg | Provide embankment around dwelling house & sheds with non-return valves on drainage outlets | 28,333 | 2019 |
Monaghan County Council | N54/R183 Junction Clones | Replace existing pipe crossings with box culvert, clean & deepen stream and stabilize banks | 189,000 | 2011 |
Galway County Council | Lugbeg River Cloughbrack Clonbur | Maintenance of river banks and vegetation removal | 16,200 | 2017 |
Sligo County Council | Strandhill | South Side Study | 11,700 | 2011 |
Clare County Council | Moynoe Scarriff | Installation of 225mm to 450mm pipe to upgrade the existing road crossing. Associated works. | 25,533 | 2019 |
Kerry County Council | Incheree | Construct new embankment of approximately 360m & access road, pipe open drains and culvert & associated works | 107,016 | 2017 |
Galway County Council | Tarramud & Coldwood Clarin River | Channel maintenance and upgrade of culverts | 40,000 | 2010 |
Waterford City & County Council | Ross Bridge Rathgormack | Re-shape riverbanks. Removal of built up gravel at bridge | 5,400 | 2010 |
Cork County Council | River Ilen Skibbereen | River cleaning | 10,000 | 2011 |
Galway County Council | Woodlawn Ballinasloe | Maintenance of 6.5m of channel | 13,500 | 2012 |
Kilkenny County Council | Gowran | Provision of flood embankment and bridge arch, widening of channel | 135,000 | 2010 |
Kerry County Council | Lough Guitane Killarney | To construct a RC flood defence wall | 13,950 | 2012 |
Galway County Council | Pribbaun Roscahill | Create a drainage channel along the boundary & feed in to historic quarry location Construct barrier/bern Associated works | 22,500 | 2014 |
Wicklow County Council | Mountain View Boghall, Bray | Install pipe | 67,500 | 2010 |
Offaly County Council | Fenter Killeigh | Works-Install drainage pipe | 22,500 | 2009 |
Cork County Council | Rossa Rd Skibbereen | Upgrade of the Rossa Road culvert trash screen & inlet chamber | 37,350 | 2020 |
Clare County Council | Kilkee Sea Wall | Underpin the existing sea walls with reinforced concrete foundation. | 81,000 | 2022 |
Monaghan County Council | Legghimore-Creevy | To upsize existing 900mm pipe to new 2.4m x 1.2m box culvert | 58,500 | 2017 |
Galway County Council | Leenaun Graveyard & Parochial House | Rock armour works | 135,000 | 2019 |
Leitrim County Council | Mountcampbell | Construction of land bank 300m x 10m above summer level, will allow river during winter to increase in width and reduce current winter levels | 47,700 | 2016 |
Dublin City Council | Raheny Village & Harmonstown Road | Works at Harmonstown Road river culvert and upstream of Harmonstown Bridge. Works between Howth Road and Raheny Main Street – Raising of embankments, replacement of walls and flap valves on pipe outlets. Modelling of Santry River | 135,000 | 2011 |
Galway County Council | Ballyglass, Kilconnell | Replace the existing culvert, new culvert will be at lower level and have greater capacity | 9,000 | 2010 |
Leitrim County Council | Canbeg Dowra | Clear away obstruction up and down stream of the bridge on the L-82281. Cut back trees that hang over the river. | 7,374 | 2014 |
Louth County Council | Dunleer | Flood Risk Management Study | 22,500 | 2018 |
Kerry County Council | Flesk River Glenflesk (phase 1 & 2) | Clearance of vegetation of the river bank between Curreal Bridge at Glenflesk Village to Gortahoosh Bridge & Loo Bridge and associated works | 152,986 | 2018 |
Cork County Council | Ballingeary | Tree & shrub removal from Inchinossig Bridge to the Bunsheelin River, on Bunsheelin River from GAA pitch to confluence with the River Lee & in an area known as “The Ford” | 22,500 | 2016 |
Clare County Council | Spanish Point | Provide rock armour over 75m | 225,000 | 2020 |
Mayo County Council | Shore Rd Bunacurry Achill | Clear vegetation downstream of access bridge to house where flooding occurred | 5,400 | 2011 |
Clare County Council | Elm Park / Watery Road | Construct higher embankment / Upgrade storm drain | 135,000 | 2010 |
Wicklow County Council | South Beach Arklow | The building up of an existing on-shore embankment. | 46,200 | 2015 |
Mayo County Council | Downpatrick Head | Works | 45,500 | 2009 |
Galway County Council | Greenfield | Raise the road by 0.35m over a 120m long section & raise the adjoining turning-head/hard standing area by circa 0.15m (tapering down to the jetties) | 17,100 | 2014 |
Kerry County Council | Dingle Bay East - Castlemaine Harbour | The procurement of additional survey work | 21,038 | 2021 |
Galway County Council | Oran Island Oranmore | Strengthen & raise the existing walls & provide flood gates to the front entrance. | 28,800 | 2019 |
Galway County Council | Cregganore, Castledaly | The upgrade & repair of existing culverts Associated works | 29,700 | 2021 |
Mayo County Council | Cloondaff Glenhest | Vegetation clearance & wall repairs | 6,660 | 2020 |
Galway County Council | Kilcommadan Aughrim Ballinasloe | Upgrade road bridge on existing watercourse | 6,030 | 2012 |
Carlow County Council | Kennedy Car Park | Construct new wall on the car park side of existing wall & carry out works to include drainage and sumps | 17,985 | 2016 |
Clare County Council | Gort Road Industrial Park Ennis | Install overflow flood culvert | 300,000 | 2010 |
Meath County Council | Swan River | Construct flood embankments | 45,000 | 2010 |
Galway County Council | Beagh Tuam | To extend a 900mm diameter pipe across the N83 | 14,220 | 2016 |
Roscommon County Council | Jamestown | Removal of trees & timber debris from river bank | 22,500 | 2019 |
Donegal County Council | Bridgend | Install additional drainage pipes & ancillary works | 34,200 | 2013 |
Sligo County Council | Finned River Easkey | Study | 6,300 | 2020 |
Kerry County Council | Ballyheigue-Banna-Carrahane & Brandon Bay Maharees (Tralee Bay) | Coastal Erosion & Flood Risk Management Study | 150,000 | 2018 |
Monaghan County Council | Rafeenan Ballinode | Construct wall/embankment, raise ground levels & provide a small pumping station | 14,400 | 2013 |
Donegal County Council | Donegal Town | Upgrade works to walls along the river bank, install 3 large diameter non-return valves, purchase flood barrier (100m), construct an earthen bund 70m, replace the existing culvert with a new culvert 3.0m wide by 1.8m high, removal of overhanging trees from the banks of the river & associated works | 369,000 | 2019 |
Galway County Council | (a)Thomastown Belclare; (b) Treenbaun Goldenpark; (c) Kilshanvy Kilconly | Combined study | 10,800 | 2010 |
Wicklow County Council | Baltinglass Town Centre | Accommodation Works – flap valves - new manhole and embankment at Church Lane | 29,800 | 2011 |
Limerick City & County Council | Redgate | Unblock culvert (enlarge if necessary) under road | 22,500 | 2011 |
Limerick City & County Council | Ballinlonnig Dromcollogher | To carry out an evaluation of current pipe structure & remedial work to include increased capacity, if required | 36,000 | 2016 |
Kerry County Council | Gallarus Ballydavid | To clean silt and sand from rivers & estuary of rivers | 6,300 | 2011 |
Kerry County Council | Flesk River (phase 1 & 2) | Clearance of vegetation of the river bank between Curreal Bridge at Glenflesk Village to Gortahoosh Bridge & Loo Bridge and associated works | 7,661 | 2020 |
Wexford County Council | St. Kiernan Bannow Bay | St. Kiernan's Coastal Protection Consultancy Study | 18,000 | 2010 |
Galway County Council | Renville West Oranmore | Carry out drainage maintenance works on approx 950m of channel | 9,000 | 2013 |
Galway County Council | Kylemore Laurencetown | Upgrade culvert | 9,000 | 2010 |
Kilkenny County Council | Fanningstown & Owning | Study | 9,000 | 2016 |
Galway County Council | Esker Ballymacward/Scarreth | Replace culvert, clean river | 18,000 | 2010 |
Galway County Council | Bride St Loughrea | Create new water pipeline and connect to existing one | 31,500 | 2010 |
Kerry County Council | N70 Garranearagh Caherciveen | Feasibility Study | 5,258 | 2015 |
Longford County Council | Camlin River – Clondra Downstream | Channel reprofiling Works | 7,200 | 2011 |
Kilkenny County Council | Knockhouse to Portnascully via Dungooley | Study | 9,000 | 2016 |
Galway County Council | Cappakeela Portumna | Upgrade the existing road crossing culvert to 900mm and to clean and re-grade where necessary approximately 100m of open channel | 9,888 | 2015 |
Galway County Council | Circular Road, Gort, Co. Galway | 13,860 | 2024 | |
Donegal County Council | Meenaniller | Study | 7,200 | 2010 |
Monaghan County Council | Drumfaldra Ballybay | Replacement of circa 50m of stream culvert, road crossing & resurfacing of road | 76,500 | 2021 |
Galway County Council | Kilcreevanty Tuam | To construct a 1.2m earthen embankment and install a flood gate barrier, along with construction of an internal collection sump and delivery pipeline with non-return valves | 14,400 | 2016 |
Donegal County Council | Bundoran Rogay beach | Rock fall protection | 90,000 | 2010 |
Dublin City Council | Dodder Estuary,Fitzwilliam Quay | Restore section of Quay Wall on Fitzwilliam Quay | 150,000 | 2011 |
Sligo County Council | Strandhill Bay | Coastal Erosion & Flood Risk Management Study | 72,000 | 2021 |
Galway County Council | Pollnahallia Turlough-Monaghan | To construct an earth embankment around the perimeter of the site | 5,940 | 2017 |
Kerry County Council | N70 Valentia Road Caherciveen | • The provision of a proper coarse grating in the stream channel, 10m upstream of the intake point • Install a headwall at the intake point to reduce head losses • Install 10m long of 1050dia pipe to replace the existing rectangular section of culvert at the start of the run. • Install 1 no. new PCC manhole to allow the 1050dia pipe to connect to the existing 700dia pipe under the hotel car park. The provision of the manhole would reduce the severity of the existing bend at this location, thus reducing head losses and allowing increased flow through the pipe. Reinstatement of paved areas and the hotel boundary wall removed to enable works to be completed | 37,633 | 2024 |
Galway County Council | Longford Portumna | Installation of 2 sections of surface water drain totalling 250m & associated works | 42,750 | 2017 |
Donegal County Council | An Seascann Beag, L-1263 | Replacement of O' Fearraigh Bridge & Fred Coll's Bridge | 78,435 | 2010 |
Kilkenny County Council | Graiguenamanagh | Channel clearance, construct wall | 198,000 | 2010 |
Longford County Council | The Mall Longford | Flood Relief Design Study for The Mall, Longford | 14,040 | 2018 |
Tipperary County Council | Curragh Goatenbridge | Cleaning of approx 200 metres of existing 1.50m deep drainage ditch /Installation of approx. 60 metres of 375mm concrete drainage pipe & drainage grates | 7,650 | 2012 |
Dun Laoghaire / Rathdown | Deansgrange Stream | Realign stream & embankment | 148,500 | 2013 |
Cork County Council | Skibbereen | Flood Risk Assessment & Management Study – Ilen Catchment River Ilen Catchment Flood Risk Assessment & Management Study: Feasbility Study & Preparation of Draft Flood Risk Plan Flood Plain & Channel Survey | 119,000 | 2011 |
Galway County Council | Blane Cross Athenry | Carry out channel maintenance and re-grading works where necessary upstream & downstream of a new culvert which is to cross the L7165 and discharge into an existing drainage channel which will be maintained by Galway County under the Drainage District works programme | 20,534 | 2015 |
Kerry County Council | Clieveragh Listowel | Study | 22,495 | 2016 |
Tipperary County Council | Grange Cremary | Install 900mm pipes to upgrade bridge capacity | 9,000 | 2012 |
Tipperary County Council | Blackcastle Rd, Templemore, Co. Tipperary | Tipperary County Council propose to construct an additional 6m culvert beside an existing bridge. TCC then intend on raising the road as well as widening an existing channel. | 181,000 | 2024 |
Kerry County Council | N70 Valentia Road, Cahersiveen | Construction of a new grating system & relaying of approx. 100m of culvert & associated works. | 35,924 | 2021 |
Galway County Council | Gloves Athenry | Installation of drainage channel | 76,500 | 2010 |
Tipperary County Council | Holy Cottage Road, Barnane, Templemore | Construction of 520m of a 450mm surface water pipe along with a number of new gullies & associated works | 13,500 | 2019 |
Donegal County Council | Eastend Bundoran | Placement of larger capacity pipes at several locations | 27,000 | 2010 |
Galway County Council | Cahermore Kinvarra | Construction of a concrete box culvert & associated road raising | 48,150 | 2013 |
Longford County Council | Cloonagh | Upgrade culvert | 13,779 | 2010 |
Mayo County Council | Leenane Owenwee | Study & Works (Study only funded) | 8,000 | 2009 |
Longford County Council | Tomiskey | Construct a 25m 1200mm diameter culvert | 16,206 | 2016 |
Galway County Council | Derreen Gort | Removal of blockages, pruning back of overhanging tree limbs & removal of trees on river bank | 22,500 | 2013 |
Longford County Council | Lisduff Lanesboro | Improve / drain the land drainage over 1 - 2kms, install a 900mm diameter pipe at main road crossing & next to dwelling to improve flow of water | 22,500 | 2017 |
Galway County Council | Kilnahown Aughrim | River channel cleaning works | 14,940 | 2017 |
Roscommon County Council | Lissalway Castlerea | Study | 2,700 | 2010 |
Mayo County Council | Salmon Leap Cottage Belclare | Divert flood waters away from house back into main channel | 9,000 | 2016 |
Galway County Council | Glenamaddy Turlough | Flood Relief Feasibility Study to include Hydrological Study, Environmental Assessment & Preliminary Design Report | 22,140 | 2021 |
Galway County Council | Cornmucklagh Ahascragh Ballinasloe | Install storm water drainage system to discharge water to open drain | 18,000 | 2010 |
Cork County Council | Ballintubber | Lay 940mm of 450mm diameter pipe from the northern boundary of the nursery (Irish Plant Propagation Ltd) to the outfall to existing stream approximately 940m south | 346,500 | 2018 |
Louth County Council | Seabank Castlebellingham | To repair the sea defence | 13,500 | 2015 |