Frequently Asked Questions


 

The current best estimate is that construction will commence in 2026, but this is subject to change. The current estimated Project Programme (at the time of writing, Autumn 2023) is as follows:
•    Stage I – Identification of Preferred Scheme: Complete by end of 2023
•    Stage II – Planning: Commence in 2024
•    Stage III – Detailed Design and Tender Process: Commence by 2025 (subject to planning consent process)
•    Stage IV – Commence in 2026

The construction start date is dependent on a number of elements: 
•    Statutory Consent
•    Option(s) chosen
•    Scale of Feedback Received
•    Site Investigation
•    Complexity of Design
•    Objections and Judicial Reviews

The current estimate for the construction period is approx. three to four years, but this is dependent on the option chosen (i.e. how complex the construction may be).

The National Development Plan 2018-2027 commits to almost €1 billion in funding for flood relief schemes, with annual Capital funding for flood relief for the OPW doubling to €100m by 2021. 

The funding is available, so long as a cost beneficial solution to resolve flooding in Midleton can be developed. The current estimate of damages associated with flooding across the Midleton area is €40 million. The total cost of the proposed scheme must not exceed this figure.

This is the best available information as of June 2020.

For the design and implementation of flood relief schemes, OPW’s preferred approach is to adopt a “Managed Adaptive Approach”.

This means that provision is made in the design of the scheme in the present day to allow it to be adapted or enhanced in the future to address climate change. The advantage of the “managed adaptive approach” is that it allows for future learning about the climate to inform on the design of flood mitigation measures for future climate scenarios. The most technically, environmentally and economically viable flood protection scheme that addresses future flood risk can therefore be implemented at the appropriate point in time in the future.  

The scheme will defend against the present-day flood risk and will be built to be adaptable to future climate change. This means that the fluvial and tidal direct defences will be constructed to be extendable (demountable or permanent), depending on the increase in levels/flow that may arise in future. Should upstream storage be the part of the final scheme, the storage will be designed to be extendable in the future.

A project specific Climate Change Adaptability Plan has been develped, which considers how climate change will impact future flood events and how the scheme will be adapted to meet the required standard in the future. This is a live document and updated throughout the project lifespan.

The present-day flows are too high to achieve the 1 in 100 year standard of protection required in Midleton by implementing Natural Flood Management (NFM) measures only. 

It was found that NFM could result a minor reduction in structural flood defences on the Owenacurra River. However given the scale of intervention required across the catchment, the costs, the landowner engagement required and the logistics of construction and maintenance, an NFM solution is not technically or economically viable as an option or even in combination with other measures in terms of reducing flood risk at Midleton. NFM measures would not contribute to any reduction in flood defence requirements on the Dungourney River as the area requiring defences is also subject to tidal flooding. Upstream storage is proposed as the emerging preferred option in Ballinacurra, which would deem other NFM features ineffective. This option could also provide potential for biodiversity and amenity benefits.

NFM could be considered as a future measure within the Climate Change Adaptability Plan to increase flood resilience subject to further investigation.

Dredging is always very challenging environmentally. In this project, we are either in the Special Protection Areas/Special Areas of Conservation or in their zones of hydrological influence. It would be very unlikely that we could achieve the environmental consents required. Extensive dredging is also considered not viable for this scheme due to the cost of ongoing maintenance.Furthermore dredging in tidal waters is not effective in reducing peak flood levels because the dredged area becomes occupied by tidal waters and is not available to take flood flows. 

However, the conveyance improvement option proposed in Area 1 does include some localised dredging as a flood alleviation measure. 

The Office of Public Works has no responsibility for oversight or regulation of the insurance industry in relation to flood risk insurance, or to insurance matters generally. The Government’s strategy is that in return to its investment on flood defence schemes in the most at risk communities, households and businesses should be able to access flood insurance.

The Office of Public Works has a very specific role in the exchange of information with the insurance industry in relation to completed flood defence schemes, to an agreed standard of protection desired by the industry. 

A Memorandum of Understanding agreed on 24th March 2014, between the Office of Public Works and Insurance Ireland, the representative body for the insurance companies in Ireland has a specific focus on agreeing a basis on which information can be provided to the insurance industry on flood relief schemes completed by the OPW. 

The Memorandum came into effect on 1st June, 2014 with an initial tranche of data provided by the Office of Public Works to Insurance Ireland in respect of twelve completed flood defence schemes; showing the design, extent and nature of the protections offered by these works.  Details of a further five schemes were provided in January 2015 and details of the Waterford Flood Defence Scheme was provided in 2017.

Since that time the level of flood insurance cover for homes and small businesses for areas protected by OPW flood defence schemes has on average increased from 77% to 82% with the level of flood insurance cover reported to be up to 90% in areas benefitting from fixed defences. 

The Department of Finance and the OPW meet with Insurance Ireland to address issues in relation to this transfer of data.  It is important to note that while the Memorandum requires that insurers take full account of information provided by the OPW on completed flood defence schemes, it does not guarantee the availability of flood risk cover in the locations for which information has been provided by the OPW. The provision of insurance cover, the level of premiums charged and the policy terms applied are a matter for individual insurers. 

Should you have any insurance related complaints or queries, you may to contact Insurance Ireland's Insurance Information Service (01 676 1914 or feedback@insuranceireland.eu).  In addition, the Financial Services Ombudsman (1890 88 20 90) deals independently with unresolved complaints from consumers about their individual dealings with all financial service providers.


 

Email: midletonfrs@arup.com

Twitter: @corkcoco

            @opwireland

Copyright 2020, All rights reserved

Privacy Statement

 

 

OPW's National Flood Information Portal - www.Floodinfo.ie