Project Timeframe
Kilkenny County Council, supported by a Steering Group including the Office of Public Works and Carlow County Council, has commissioned ByrneLooby to develop and implement a Flood Relief Scheme for Graiguenamanagh-Tinnahinch. The project comprises of five stages (Note: Dates are a best estimate at time of writing)
Stage 1
Scheme Development and Preliminary Design
Completed by Q4 2022
Stage 2
Planning Statutory Delivery Route and Public Exhibition
Completed by Q3 2023
Stage 3
Detailed Design, Confirmation and Tender
Completed by Q4 2023
Stage 4
Construction Supervision
Completed by Q4 2025
Stage 5
Handover of Works
Completed by Q1 2027
Stage 1 – Scheme Development and Preliminary Design
- Hydrometeric and Environmental Surveys
- Hydrological and Hydraulic Analysis of the watercourses
- Flood relief options apraisal and selection
- Environmental Assessments
- Public Consultation
Stage 2 – Planning Statutory Delivery Route and Public Exhibition
- Planning Application process
- Public Exhibtion
Stage 3 – Detailed Design, Confirmation and Tender
- Detailed structural design of Final Option
- Ministerial Confirmation
- Tendering for construction services