Project Timeframe

Stage

Description

Completion

Stage 3

Detailed Construction Design and Tender

Q3 2025

Stage 4

Construction

2029

Stage 5

Handover of Works

2030


 

Stage 3 – Detailed Construction Design and Tender

Stage III will involve detailed design, preparation of tender documents and a public competition to appoint a main works contractor(s).

Stages 4 – Construction

Construction will be carried out by a works contractor(s), under supervision of the consultant, following a public procurement competition. A functioning scheme will be in place at the end of stage 4.

Stages 5 – Handover of Works

Commision of the completion certificate. Preparation of a financial analysis report for the project. 'As-Built' surveys, 'As-Built' flood mapping and an updated Climate Change Adaptation plan will be prepared.