Project Timeframe
Stage
Description
Completion
Stage 3
Detailed Construction Design and Tender
Q3 2025
Stage 4
Construction
2029
Stage 5
Handover of Works
2030
Stage 3 – Detailed Construction Design and Tender
Stage III will involve detailed design, preparation of tender documents and a public competition to appoint a main works contractor(s).
Stages 4 – Construction
Construction will be carried out by a works contractor(s), under supervision of the consultant, following a public procurement competition. A functioning scheme will be in place at the end of stage 4.
Stages 5 – Handover of Works
Commission of the completion certificate. Preparation of a financial analysis report for the project. ‘As-Built’ surveys, ‘As-Built’ flood mapping and an updated Climate Change Adaption plan will be prepared.