Project Timeframe
Tipperary County Council, supported by a Steering Group including the Office of Public Works, has commissioned Ayesa to develop and implement a Flood Relief Scheme for Ballina. The project comprises of five stages (Note: Dates are a best estimate at time of writing)
Stage 1
Scheme Development and Preliminary Design
Completed by Q4 2023
Stage 2
Planning Statutory Delivery Route and Public Exhibition
Completed by Q3 2024
Stage 3
Detailed Design, Confirmation and Tender
Completed by Q2 2025
Stage 4
Construction Supervision
Completed by Q1 2026
Stage 5
Handover of Works
Completed by Q4 2026
Stage 1 – Scheme Development and Preliminary Design
- Hydrometric and Environmental Surveys
- Hydrological and Hydraulic Analysis of the watercourses
- Flood relief options appraisal and selection
- Environmental Assessments
- Public Consultation
Stage 2 – Planning Statutory Delivery Route and Public Exhibition
- Planning Application process
- Public Exhibition
Stage 3 – Detailed Design, Confirmation and Tender
- Detailed structural design of Final Option
- Ministerial Confirmation
- Tendering for construction services
Stages 4 – Construction Supervision
Stages 5 – Handover of Works