Project Timeframe


 

To advance and implement a Flood Relief Scheme for Buncrana and Luddan, Donegal County Council, supported by a Steering Group including the OPW, has commissioned Ayesa to develop and implement the flood relief scheme. The project shall comprise up to five stages, as shown below:

 

Stage I: Scheme Development and Design

Stage I will involve the collection of all relevant data. Relevant surveys will be prepared, tendered and managed in line with national guidance and best practice.  Following collection of this data, hydrological and hydraulic analysis of the study area will be carried out.  A full cost-benefit analysis of the Scheme will also be undertaken.

 

Stage II: Planning

Stage II will involve preparation of all documentation, including environmental documentation, required to progress the Scheme through the necessary planning, including public display, and other statutory processes.

 

Stage III: Detailed Construction Design and Tender

 

Stage III will involve detailed design, preparation of tender documents and a public competition to appoint a main works contractor.

 

Stage IV: Construction

Construction will be carried out by a works contractor, under supervision of the consultant, following a public procurement competition. A functioning scheme will be in place at the end of stage IV.

 

Stage V: Handover of Works

Commission of the completion certificate. Preparation of a financial analysis report for the project.  ‘As-Built’ surveys, ‘As-Built’ flood mapping and an updated Climate Change Adaption plan will be prepared.

 

 

 

 

 

 

 

 

 

Postal address: Ayesa, Building 2100, Cork Airport Business Park, Kinsale Road, Cork. T12 KV8R

Telephone: +353 (0)21 240 7988

Email: BuncranaFRS@Ayesa.com

 

 

 

 

 

 

 

 

Copyright 2021, All rights reserved

Privacy Statement

 

 

OPW's National Flood Information Portal - www.Floodinfo.ie