Project Timeframe
The Athy Flood Relief Scheme will be delivered in 5 stages with indicative timeframes as follows:
Stage 1
Identification and Development of a Preferred Scheme
2023 - 2026
Stage 2
Planning/Development Consent
2026 - 2027
Stage 3
Detailed Construction Design, Work Packages and Tenders for Contracts
2026 - 2028
Stage 4
Construction
2028 - 2030
Stage 5
Handover of Works
2030 - 2031
Stage 1 – Option Identification and Scheme Design
- Carry out the review and assessment of the technical analysis of existing information in relation to the Scheme area.
- Identify and undertake all baseline environmental surveys and site investigations.
- Hydrological and hydraulic modelling, and production of revised mapping, of the existing situation.
- Environmental Constraints Study
- Production of Invasive Species Management Plan
- Assessment, including technical, geotechnical, environmental, and economic assessments, and through detailed hydraulic modelling, of potential flood risk management options.
- Consideration and identification of advance works contracts
- Selection, development, and design of a preferred scheme option.
- Identification of Landowners that may be affected by the construction, operation, and future maintenance of the Scheme.
- Produce a Natura Impact Statement (NIS), Environmental Impact Assessment Report (EIAR), Preliminary Construction Environmental Management Plan (CEMP), Natural Water Retention Measures (MWRM) Maps, Climate Change Adaption Plan, Preliminary Buildability and Preliminary Operation & Maintenance Reports
Stage 2 – Development Consent
- Provision of all documentation required to progress the Scheme through the necessary statutory development consent process (Planning and Development Act 2000 or Arterial Drainage Act 1945).
- Provision of responses to Further Information or Clarification requests.
- Provision of support at Public Displays and Oral Hearings.
- Provision of addendums to the Environmental Assessments as a result of the outcomes/conditions of the development consent process
- Provision of detailed design drawings and specifications.
Stage 3 - Construction Works Procurement
- Undertake and complete the detailed construction design of the Scheme.
- Update or provide addendums to the environmental assessments undertaken in Stage I, and complete any other environmental assessments, consents, or surveys.
- Produce a Developed Construction Environmental Management Plan (CEMP) ,a Developed Buildability Report and a Developed Operation & Maintenance Report
- Prepare Detailed Design Drawings and Specifications
- Determine Construction Work Packages
- Prepare Tender & Construction Work Packages including Bills of Quantities
- Prepare Construction Contract Documents using the PWC Forms of Contract and undertake the procurement of the works contractor(s) to construct the Scheme, in line with the Capital Works Management Framework
- Preparation of Tender Report(s)
Stage 4 – Construction Works
- Supervise the construction of the Scheme
- Supervise the construction contract(s) and provide Project Management Services including Employer Representative services.
Stage 5 – Handover of Works
- Commissioning of the completion certificate
- Provision of a Financial Analyst Report
- Finalisation/sign-off of Construction Contracts
- Provision of the Safety File
- Produce “As-Built” flood mapping