Togher Traffic Management Arrangements June/July 2022 

 

Below please see the Traffic Management Plans for the current and upcoming phases of work. They include separate plans for:

 

1.  Road Closure for resurfacing - Togher Road North (Applegreen to Westside Estate) - Details

2.  Road Closure for resurfacing - Togher Road North (Applegreen to Westside Estate) - Detours

3.  Roundabout excavation and resurfacing - Phase 1

4.  Roundabout excavation and resurfacing - Phase 2

5.  Storm Sewer Connection - Lehenaghmore Road (between Roundabout and Brook Avenue)

6.  Storm Sewer connection - Lehenaghmore Road (outside Lehenaghmore Industrial Estate)

Please note that there are regularly minor amendments to these plans to accomodate day to day activities. 

Additionally please see link below to a newsletter that is being sent to residents which sumarises what works have been done to date and what remains be be completed.

Contractor Update Letter June 2022

We understand that the works are causing disruption to the area and we thank you for your continued patience as we continue to progress with the project as efficiently and safely as possible. 


 

Email: douglasfrs@arup.com 