Project Timeframe

The Athy Flood Relief Scheme will be delivered in 5 stages with indicative timeframes as follows:

 

Stage 1

Identification and Development of a Preferred Scheme

2023 - 2026

Stage 2

Planning/Development Consent

2026 - 2027

Stage 3

Detailed Construction Design, Work Packages and Tenders for Contracts 

2026 - 2028

Stage 4

Construction

2028 - 2030

Stage 5

Handover of Works 

2030 - 2031

 


 

Stage 1 – Option Identification and Scheme Design 

  • Carry out the review and assessment of the technical analysis of existing information in relation to the Scheme area.
  • Identify and undertake all baseline environmental surveys and site investigations.
  • Hydrological and hydraulic modelling, and production of revised mapping, of the existing situation.
  • Environmental Constraints Study
  • Production of Invasive Species Management Plan
  • Assessment, including technical, geotechnical, environmental, and economic assessments, and through detailed hydraulic modelling, of potential flood risk management options.
  • Consideration and identification of advance works contracts
  • Selection, development, and design of a preferred scheme option.
  • Identification of Landowners that may be affected by the construction, operation, and future maintenance of the Scheme.
  • Produce a Natura Impact Statement (NIS), Environmental Impact Assessment Report (EIAR), Preliminary Construction Environmental Management Plan (CEMP), Natural Water Retention Measures (MWRM) Maps, Climate Change Adaption Plan, Preliminary Buildability and Preliminary Operation & Maintenance Reports

 

Stage 2 – Development Consent

  • Provision of all documentation required to progress the Scheme through the necessary statutory development consent process (Planning and Development Act 2000 or Arterial Drainage Act 1945).
  • Provision of responses to Further Information or Clarification requests.
  • Provision of support at Public Displays and Oral Hearings.
  • Provision of addendums to the Environmental Assessments as a result of the outcomes/conditions of the development consent process
  • Provision of detailed design drawings and specifications.

 

Stage 3 - Construction Works Procurement 

  • Undertake and complete the detailed construction design of the Scheme.
  • Update or provide addendums to the environmental assessments undertaken in Stage I, and complete any other environmental assessments, consents, or surveys.
  • Produce a Developed Construction Environmental Management Plan (CEMP) ,a Developed Buildability Report and a Developed Operation & Maintenance Report
  • Prepare Detailed Design Drawings and Specifications
  • Determine Construction Work Packages
  • Prepare Tender & Construction Work Packages including Bills of Quantities
  • Prepare Construction Contract Documents using the PWC Forms of Contract and undertake the procurement of the works contractor(s) to construct the Scheme, in line with the Capital Works Management Framework
  • Preparation of Tender Report(s)

 

Stage 4 – Construction Works 

  • Supervise the construction of the Scheme
  • Supervise the construction contract(s) and provide Project Management Services including Employer Representative services.

 

Stage 5 – Handover of Works

  • Commissioning of the completion certificate
  • Provision of a Financial Analyst Report
  • Finalisation/sign-off of Construction Contracts
  • Provision of the Safety File
  • Produce “As-Built” flood mapping

Postal Address:    Athy Flood Relief Scheme – Project Manager

                             RPS Consulting Engineers, West Pier Business Park, Dún Laoghaire

                             Co.Dublin, A96 N6T7, Ireland.

Email:                    athyfrs@rpsgroup.com

Copyright 2020, All rights reserved

Privacy Statement

 

Steering Group Members:

     

 

 

OPW's National Flood Information Portal - www.Floodinfo.ie